PT 1 Construction updates

View PT 1 Construction updates flipbook.

Plastering work on the south side exterior wall is in progress

Scaffolding and platforms preparation on the east side exterior wall is in progress

Third floor is ready for MEP Works

Third floor is ready for MEP Works

Second floor is ready for MEP Works

First Floor is ready for MEP works except for the place occupied by equipment and Gamma's temporary office

Ground Floor is ready for MEP works except for the place occupied by the WWT equipment.

Brickwork for the ground floor internal rooms on the north side is currently underway.

Ground floor internals room brickwork- Southside (Electric room and ventilation shaft)

Ground floor internals room brickwork- Northside (Spandex yarn storage and HR)

Ground floor internals room brickwork- Northside (Admin lobby)

Installing Bracing's and Purling's for Sub roof

Dyeing house Mezzanine area

Steel fixing for the north and Eastside tunnel slab in progress. Bitumen sheet installation and backfilling are underway.

First and second phase of steel erection are about 60% finished. remaining 40% is on hold as the foundations are not yet ready for erection ( Near the WWT area)

Basement foundation preparation for the dyeing house, located between the Tunnel and the Admin building, is in progress.

An internal view of the east side tunnel

An internal view of the north side tunnel

Bitumen sheet installation and backfilling are under progress in northside.

Lucas Tank-C Injection treatment complete, and the tank is ready for isolation work

Lucas Tank-A, Injection treatment under progress

Lucas Tank- A, water level has reached 6mtrs.

Sludge storage tank concrete repair under progress

Lamella Settler Tank, Cleaning work on going

Coagulation Tank, Reaction tank and Water treated Tank, concrete repair and cleaning under progress

LABO. & CONTROL ROOM

TECHNICAL AREA, column steel fixing and shuttering are in progress

RO Tank basement preparation on progress

CHEMICAL TANK AND VEHICLE MOVEMENT AREA

EQUALIZATION TANK, Concrete repairs under progress

Administration Building, Second phase first floor Tie beam steel fixing and timber shuttering on going

Administration Building, First phase second floor roof shuttering preparation on going

Administration Building, ground floor soil filling and brickwork's under progress.

Shutter and scaffolding removal at the Boiler house is currently underway

LOGISTICS BUILDING, First phase column steel fixing and shuttering under progress

The installation of shoring piles near the equalization tank are is in progress

Plastering work on the south exterior wall

Plastering work on the south exterior wall