View PT 1 Construction updates flipbook.
Plastering work on the south side exterior wall is in progress
Scaffolding and platforms preparation on the east side exterior wall is in progress
Third floor is ready for MEP Works
Third floor is ready for MEP Works
Second floor is ready for MEP Works
First Floor is ready for MEP works except for the place occupied by equipment and Gamma's temporary office
Ground Floor is ready for MEP works except for the place occupied by the WWT equipment.
Brickwork for the ground floor internal rooms on the north side is currently underway.
Ground floor internals room brickwork- Southside (Electric room and ventilation shaft)
Ground floor internals room brickwork- Northside (Spandex yarn storage and HR)
Ground floor internals room brickwork- Northside (Admin lobby)
Installing Bracing's and Purling's for Sub roof
Dyeing house Mezzanine area
Steel fixing for the north and Eastside tunnel slab in progress. Bitumen sheet installation and backfilling are underway.
First and second phase of steel erection are about 60% finished. remaining 40% is on hold as the foundations are not yet ready for erection ( Near the WWT area)
Basement foundation preparation for the dyeing house, located between the Tunnel and the Admin building, is in progress.
An internal view of the east side tunnel
An internal view of the north side tunnel
Bitumen sheet installation and backfilling are under progress in northside.
Lucas Tank-C Injection treatment complete, and the tank is ready for isolation work
Lucas Tank-A, Injection treatment under progress
Lucas Tank- A, water level has reached 6mtrs.
Sludge storage tank concrete repair under progress
Lamella Settler Tank, Cleaning work on going
Coagulation Tank, Reaction tank and Water treated Tank, concrete repair and cleaning under progress
LABO. & CONTROL ROOM
TECHNICAL AREA, column steel fixing and shuttering are in progress
RO Tank basement preparation on progress
CHEMICAL TANK AND VEHICLE MOVEMENT AREA
EQUALIZATION TANK, Concrete repairs under progress
Administration Building, Second phase first floor Tie beam steel fixing and timber shuttering on going
Administration Building, First phase second floor roof shuttering preparation on going
Administration Building, ground floor soil filling and brickwork's under progress.
Shutter and scaffolding removal at the Boiler house is currently underway
LOGISTICS BUILDING, First phase column steel fixing and shuttering under progress
The installation of shoring piles near the equalization tank are is in progress
Plastering work on the south exterior wall
Plastering work on the south exterior wall