OIP-02-03, Rev.1.0 Final Report HTU APPRENTICESHIP JOURNEY School of Built Environment Engineering By: Farah Abuzaid 20/9/2026 Apprenticeship Final Report Student Name: Farah Abuzaid Student ID: 22110059 Major: Architectural Engineering Apprenticeship Mentor: Eng . Hamza Bustanji Company Name: AJi group company Industry Mentor: Eng. Jomana Alawi Dates: 15/2/2026 - 15/10/2026
OIP-02-03, Rev.1.0 Final Report TABLE OF CONTENTS HTU Apprenticeship Journey ..................................................................................................... Apprenticeship Final Report ..................................................................................................... General Introduction: ................................................................................................................ Detailed Description of the program ....................................................................................... SECTION 1:............................................................................................................................... 1st Month Report .................................................................................................................... 2nd Month Report .................................................................................................................. 3rd Month Report ................................................................................................................... 4th Month Report ................................................................................................................... 5th Month Report ................................................................................................................... 6th Month Report ................................................................................................................... 7th Month Report ................................................................................................................... 8th Month Report ................................................................................................................... SECTION 2 :.............................................................................................................................. SECTION 3 :..............................................................................................................................
OIP-02-03, Rev.1.0 Final Report OVERALL COM PETENCY ACHIEVEMENT – 8-MONTH APPRENTICESHI P Chapter Name of NOS: Number of NOS: Completed % : 1 Programming & Analysis (Pre Design Phase) 11/15 73.33% 2 Project Planning & Conceptual Design 11/17 64.71% 3 Design Development, Detailed Design and Construction Informtion 18/29 62.07% 4 Project Management 21/30 73.33% 5 Supervision 19/32 59.38% 6 Construction Management 7/11 63.64 Total Completed 65.67% GENERAL INTRODUCTION: NAME OF COM PANY AJi Group AJi, formerly known as Arabtech Jardaneh Group, represents a new chapter for the company, with the “i” reflecting its four core values: Innovation, Integration, Integrity, and Inclusivity.
OIP-02-03, Rev.1.0 Final Report ABOUT T HE COMPANY AJi Group is a regional architecture and engineering consultancy with a multidisciplinary approach covering architecture, engineering, project management, urban environments, healthcare, infrastructure, mobility, sustainability, and advisory services across the MENA region. The company combines local expertise with international capabilities to deliver integrated solutions throughout the project lifecycle, from planning and design to construction and project management. AJi also operates Yellow Lab, its dedicated design venture focusing on advanced concept design, visualization, computational design, and immersive digital experiences. DEPARTM ENTS & MY ROLE DURING THE APPR ENTICESHIP AJi Group operates through multidisciplinary departments including Architecture, Engineering, Project Management, BIM, Advisory & Solutions, and Facilities Management. During my apprenticeship, I was mainly part of the Design Department and Yellow Lab, focusing on architectural design, visualization, and digital design workflows. I mainly worked within the Design Department and Yellow Lab, contributing to architectural design, 3D modelling, visualization, and design development across different projects.
OIP-02-03, Rev.1.0 Final Report DETAILED DESCRIPTION OF THE PROGRAM 8 Months Journey Overall SECTION 1: COMPANY WORK (TASKS & PROJECTS) The following section presents my 8-month apprenticeship journey, organized month by month. Each Monthly Report documents the work completed during the month, supported by evidence, drawings, visuals, and attendance sheets. In addition, the NOS Competencies achieved during each month are presented, showing which competencies were developed and how they were achieved through the assigned tasks and projects.
OIP-02-03, Rev.1.0 Final Report 1ST MONTH REPORT 15/2/2026-15/3/2026
Email 22110059@htu.edu.jo Phone 0799864046 Address Amman Apprenticeship ReportSchool of Built Environment Engineering Apprenticeship Monthly Report Student Name: Farah Abuzaid Student ID: 22110059 Major: Architectural Engineering Apprenticeship Mentor:Arch. Jomana Alawi Company Name: AJi group Industry Mentor: Eng . Hamza Bustanji Date of Report:2/15/2026 Report Type: First Monthly Report Dates: 2/15/2025 – 3/16/2025
Table of Contents I. Apprenticeship Monthly Report ........................................................................1 II. General Introduction ..........................................................................................1 A. General Company Overview ........................................................................................... 1 B. Apprenticeship Duration and Phase Progression ......................................................... 2 III. Section 1: Office Work (Design Phases) ............................................................2 Project 1 ......................................................................................................................................... 2 Task 1 :............................................................................................................................................ 2 Task 2 :............................................................................................ Error! Bookmark not defined. IV. Project 2 ............................................................... Error! Bookmark not defined. Task 1 :............................................................................................ Error! Bookmark not defined. Task 2 :............................................................................................ Error! Bookmark not defined. V. Project 3 ...............................................................................................................3 Task 1 :............................................................................................................................................ 3 Task 2 :............................................................................................................................................ 4 VI. Project 4 ...............................................................................................................6 Task 1 :............................................................................................................................................ 7 Task 2 :............................................................................................ Error! Bookmark not defined. VII. List of Achieved Competencies .........................................................................9 VIII. Section 2 : Site Supervision ............................................................................. 17 IX. Section 3 : Project Management...................................................................... 17 X. Section 4: Executive Summary ........................................................................ 17 XI. Appendices........................................................................................................ 20
Farah’s Monthly Report PG. 1OIP-02-01, Rev.1.0 General Introduction AJi is a regional architecture and engineering pioneer building on a deep legacy of forward-looking projects in the MENA region. There multidisciplinary local capabilities are integrated with top global talent for a perfectly choreographed and executed approach to each client’s project. A. General Company Overview → Year Established: 1992 → Company Formal Name: AJi Group → Company Structure: Multidisciplinary engineering and consulting firm (Private / Limited Liability – confirm exact legal form) → Key Projects:
Farah’s Monthly Report PG. 2OIP-02-01, Rev.1.0 B. Apprenticeship Duration and Phase Progression → Start Date: 2/15/2025 → End Date: 10/15/2026 → Department / Team: architectural department – yellow team Section 1: Office Work (Design Phases) Project 1 Project Name: Al hashemiya vocational school for boys Project Location: Jordan, Amman Project Phase: Design Development DD Description of Project: Task 1 : Prepared full architectural annotations for three floors, including dimensions, door tags, and window tags. Detailed Program
Farah’s Monthly Report PG. 3OIP-02-01, Rev.1.0 List of Achieved Competencies: Code Competency Description Type CD13- 04: Communicate design ideas with BIM software. Preformance DD 09-01 Develop construction drawings (plans, sections, elevations, wall sections, details, schedules) Preformance Project 2 Project Name: Dubai Bay Island - island B Project Location: Dubai Project Phase: Pre-design studies Description of Project: Task 1 : Site Analysis Tasks for a Competition Project in Dubai – studying the location, sun path, wind, roads, surrounding buildings, and SWOT analysis.+ Regulatory Review – checking zoning laws, building codes, and permits.
Farah’s Monthly Report PG. 4OIP-02-01, Rev.1.0 Task 2 : Regulatory Review – checking zoning laws, building codes, and permits. By converting the regulations into diagrams, massing study to imagine how the space will fit on the site and what the limits are. The requirement: create diagrams that transform the regulations into visuals – massing study. Task 3 : Making the nartives and moodboudsn
Farah’s Monthly Report PG. 5OIP-02-01, Rev.1.0 Task 4 : landscape design → feedback taken for the first landscape option from Eng.Ali + i have to change the idea > according to Eng.Ali comments List of Achieved Competencies:
Farah’s Monthly Report PG. 6OIP-02-01, Rev.1.0 Code Competency Description Type PD02 Perform Site analysis (Context, climate, approach and access, environment, views, solar access, noise, etc.). Preformance PD02- 01 Prepare site analysis diagrams to document existing conditions, features, infrastructure, and regulatory requirements Preformance PD01 Determine impact of applicable zoning and development ordinances to determine project constraints. Preformance CD06 Perform massing and volumetric studies. Preformance CD13- 02 Communicate design ideas with two-dimensional (2-D) computer aided design software. Preformance CD13- 03 Communicate design ideas with three-dimensional (3-D) computer aided design software. Preformance CD10 Design landscape elements for site Knowledge Project 3 Project Name: Tuaja Al Madinah Project Location: ALMadinah AL Munawwarah, KSA Project Phase: Pre-design studies Description of Project:
Farah’s Monthly Report PG. 7OIP-02-01, Rev.1.0 Task 1 : Implementing client comments as shown in the images .
Farah’s Monthly Report PG. 8OIP-02-01, Rev.1.0 → Before → After
Farah’s Monthly Report PG. 9OIP-02-01, Rev.1.0 List of Achieved Competencies: project 3 Code Competency Description Type CD05 Prepare conceptual design alternatives Preformance CD11 Convert sketches into technical drawings Preformance CD13- 03 Communicate design ideas with 3D software Preformance CD01 Perform building code analysis Preformance PD07 Establish project design goals Preformance Project 4 Project Name: VOCO hotel Project Location: Jordan – Aqaba Project Phase: Design Development DD Description of Project: Task 1 : Reviewing detailed design + implementing client comments (staff area re-planning) Reviewed the detailed design drawings of the VOCO Hotel project and implemented client comments related to staff areas, including spatial reconfiguration, circulation improvements, and functional zoning adjustments to enhance privacy, accessibility, and operational efficiency. → Before
Farah’s Monthly Report PG. 10OIP-02-01, Rev.1.0 → After ▪ Don’t change ▪ Replace ▪ Keep the area tha same ▪ Proposed solution List of Achieved Competencies:
Farah’s Monthly Report PG. 11OIP-02-01, Rev.1.0 Code Task NO : Competency Description Type PD06 separating prayer rooms Prepare diagrams illustrating spatial relationships and functional adjacencies Preformance PD07 Establish project design goals Establish project design goals Preformance PD10 Gather information about client’s vision and requirements Preformance CD05 Prepare conceptual design alternatives Preformance CD04 Relocating toilets internally to reduce humidity impact Adjusting male/female ratio (70% / 30%) Determine human comfort levels Preformance CD01 Adjusting male/female ratio (70% / 30%) Perform building code analysis Preformance DD01 Coordinating column relocation with structural team Coordinate design work of consultants Preformance DD07 Integrating circulation with structural constraints Connecting housekeeping zones efficiently Develop and integrate building systems design solutions Preformance
Farah’s Monthly Report PG. 12OIP-02-01, Rev.1.0 Project 5 Project Name: AJWE Building Project Location: Jordan – Amman Project Phase: Design Development DD Description of Project : The project involves the interior redesign and spatial reorganization of the AJWE Department offices. The primary goal is to enhance the office environment and workflow by replanning the interior layouts and updating the color schemes and materials to create a more productive and professional atmosphere. Task 1 : office replanning ( interior design ) • Analyzed the existing office layout to identify spatial inefficiencies. • Proposed a new furniture and partition layout to optimize circulation and maximize the use of available space for the AJWE team. Task 2 : mood boards ( Images + materials ) • Curated a selection of materials, finishes, and color palettes aimed at improving the indoor environment.
Farah’s Monthly Report PG. 13OIP-02-01, Rev.1.0 Task 3 : Presentation ( Light Rendering + PowerPoint ) • Developed basic 2D visualizations (Light Rendering) to communicate the proposed design changes to the client. • Prepared a comprehensive PowerPoint presentation to showcase the design concept, mood boards, and final spatial solutions. AJWE Presentation (1)
Farah’s Monthly Report PG. 14OIP-02-01, Rev.1.0
Farah’s Monthly Report PG. 15OIP-02-01, Rev.1.0
Farah’s Monthly Report PG. 16OIP-02-01, Rev.1.0 List of Achieved Competencies: Code Task NO : Competency Description Type PD07 1 Establish project design goals Preformance PD10 1 Gather information about client’s vision, goals, and requirements Preformance CD05 1 Prepare conceptual design alternatives for client review Preformance CD13- 02 1 Communicate design ideas using 2D CAD Preformance CD03 2 Select materials, finishes, and systems based on technical and aesthetic requirements Preformance CD13 2 Communicate design ideas graphically Preformance CD13- 02 3 Communicate design ideas with 2D software Preformance CD13- 03 3 Communicate design ideas with 3D visualization / rendering Preformance
Farah’s Monthly Report PG. 17OIP-02-01, Rev.1.0 CD12 3 Present conceptual design ideas orally Preformance Section 2 : Site Supervision Section 3 : Project Management Section 4: Executive Summary 1. Any problems / Challenges and how did you overcome them? Problems with objections at the university, time constraints, and fatigue – difficulty in finding tasks – issues with personal laptops, and at the company the files are large, so we can’t always work on their devices. 2. Any training courses you attended during the apprenticeship, whether you opted for independently or through the employer. Name of the course Main Topics Certificate (Include merged file in appendices or attach a copy) 3. Technical and non-technical skills ▪ Technical • ID • Illustrator ▪ Non Technical • Team work
Farah’s Monthly Report PG. 18OIP-02-01, Rev.1.0 4. Did you work on the competencies: ▪ Over-All Achieved Competencies: Code Competency Name Project No. Type PD01 Determine impact of applicable zoning and development ordinances to determine project constraints P2 Performance PD02 Perform Site analysis (Context, climate, approach and access, environment, views, solar access, noise, etc.) P2 Performance PD02- 01 Prepare site analysis diagrams to document existing conditions, features, infrastructure, and regulatory requirements P2 Performance PD06 Prepare diagrams illustrating spatial relationships and functional adjacencies P4 Performance PD07 Establish project design goals P3, P4, P5 Performance PD10 Gather information about client’s vision, goals, budget, and schedule to validate project scope and program P4, P5 Performance CD01 Perform building code analysis P3, P4 Performance CD03 Select materials, finishes, and systems based on technical properties and aesthetic requirements P5 Performance CD04 Determine human comfort levels and corresponding design parameters for building engineering systems P4 Performance CD05 Prepare conceptual design alternatives for client review P3, P4, P5 Performance CD06 Perform massing and volumetric studies P2 Performance CD11 Convert sketches into technical drawings P3 Performance CD12 Present conceptual design ideas orally P5 Performance
Farah’s Monthly Report PG. 19OIP-02-01, Rev.1.0 CD13 Communicate design ideas graphically P5 Performance CD13- 02 Communicate design ideas with two-dimensional (2- D) computer aided design software P2, P5 Performance CD13- 03 Communicate design ideas with three-dimensional (3-D) computer aided design software P2, P3, P5 Performance CD13- 04 Communicate design ideas with BIM software P1 Performance DD01 Coordinate design work of consultants P4 Performance DD07 Develop and integrate building systems design solutions P4 Performance DD09- 01 Develop construction drawings (plans, sections, elevations, wall sections, details, schedules) P1 Performance 5. Any Events / Conferences you participated → Ramadan iftar → Group lunch → Mansaf for lunch
Farah’s Monthly Report PG. 20OIP-02-01, Rev.1.0 6. Your Plan for Next Month. Appendices Training Plan Bi-weekly Report Apprenticeship Documentation\monthly report 1\01- Report\(1) Weekly Report.xlsx Monthly Attendance Sheet Apprenticeship Documentation\monthly report 1\01- Report\(1) Daily Apprenticeship Attendance Sheet.xlsx Workplace Evaluation Form Apprenticeship Documentation\monthly report 1\01- Report\(1) Monthly Evaluation Form.docx
Month: one / 15 feb Date Day Time In Time Out Total Hours Apprentice Signature 1 2/15/2026 Sunday 8:15 AM 5:15 PM 9 HRS 2 2/16/2026 Monday 8:15 AM 5:12 PM 9 HRS 3 2/17/2026 Tuesday 9:45 AM 3:25 PM 6 HRS 4 2/18/2026 Wednesday 8:50 AM 5:45 PM 9 HRS 5 2/19/2026 Thursday 9:00 AM 3:45 PM 6.5 HRS 6 20/2/2026 Friday 7 21/2/2026 Saturday 8 22/2/2026 Sunday 8:00 AM 2:30 PM 6.5 HRS 9 23/2/2026 Monday 10:30 AM 4:30 PM 6 HRS 10 24/2/2026 Tuesday 8:00 AM 2:10 PM 6 HRS 11 25/2/2026 Wednesday 9:00 AM 2:20 PM 5.5 HRS 12 26/2/2026 Thursday 6- 13 27/2/2026 Friday 14 28/2/2026 Saturday 15 1/3/2026 Sunday 9:30 AM 4:00 PM 6.5 HRS 16 2/3/206 Monday 6- 17 3/3/2026 Tuesday 9:30 AM 3:30 PM 6 hrs 18 4/3/206 Wednesday 8:00 AM 2:00 PM 6 hrs 19 5/3/2026 Thursday 6- 20 6/3/2026 Friday 21 7/3/2026 Saturday 22 8/3/2026 Sunday 9:30 AM 4:00 PM 6.5 HRS 23 9/3/2026 Monday 1:00 PM 5:00 PM 4 hrs 24 10/3/2026 Tuesday 8:00 AM 5:00 PM 9 hrs 25 11/3/2026 Wednesday 8:00 AM 5:00 PM 9 hrs 26 12/3/2026 Thursday 1:00 PM 5:00 PM 4 hrs 27 13/3/2026 Friday 28 14/3/2026 Saturday 29 15/3/2026 Sunday 8:00 AM 5:00 PM 9 hrs 30 16/3/2026 Monday 1:00 PM 5:00 PM 4 hrs Attendance Total 27 Daily Apprenticeship Attendance Sheet Workplace mentor: AJi group Eng . Hamza Bustanji Apprentice Name: Farah Abuzaid Workplace Name: Workplace mentor Signature:
OIP-02-02, Rev.1.0 NOS Report Form NOS REPORT MONTH 1 STUDENT NAME: FARAH ABUZAID COMPANY: AJI GROUP Chapter Name of NOS: Number of NOS: 1 Programming & Analysis (Pre Design Phase) 7 2 Project Planning & Conceptual Design 11 3 Design Development, Detailed Design and Construction Informtion 3 4 Project Management 0 5 Supervision 0 6 Construction Management 0 **Performance criteria of the NOS and how you applied it in your company ** Include all the Competencies (Code/The Competency/How you applied it) (Explain and include evidence from your work)
OIP-02-02, Rev.1.0 NOS Report Form Chapter 1 PROGRAMMING & ANALYSIS (PRE DESIGN PHASE) 1.1 RELATED PROJECTS : I will use the Project No. listed in the table below as a reference for each competency. For more details on how each competency was achieved, please refer to the corresponding monthly reports submitted with this NOS report. Project name Project No. Al hashemiya vocational school for boys P1 Dubai Bay Island - island B P2 Tuaja Al Madinah P3 VOCO hotel P4 AJWE Building P5 1.2 COMPETENCY ACHIEVEMENT Competencies Details Coverage Status Category Related project NO. How the Competency Was Achieved No. Competency PD01 Determine the impact of applicable zoning and development ordinances to identify project constraints. ✓ Performance Knowledge P2 P2: Reviewed zoning laws, building codes, and permit requirements and translated them into diagrams to identify site constraints. PD02 Perform site analysis, including context, climate, approach and access, environment, views, solar access, noise, and other relevant factors. ✓ Performance Knowledge P2 P2: Studied the site location, sun path, wind, roads, surrounding buildings, and SWOT analysis. PD02- 01 Prepare site analysis diagrams to document existing conditions, site features, infrastructure, and regulatory requirements. ✓ Performance Knowledge P2 P2: Prepared site analysis and regulatory diagrams to visually document site conditions and requirements. PD02- 02 Evaluate the opportunities and constraints of alternative sites. ✗ Performance Knowledge - PD02- 03 Determine the impact of environmental, zoning, and other regulations on the site. ✗ Performance Knowledge - PD03 Evaluate the results of feasibility studies to determine the project’s financial viability. ✗ Performance Knowledge - PD04 Establish sustainability goals affecting building performance. ✗ Performance Knowledge -
OIP-02-02, Rev.1.0 NOS Report Form PD05 Apply a checklist of potential strategies with reference to green building rating systems. ✗ Performance Knowledge - PD06 Prepare diagrams illustrating spatial relationships and functional adjacencies. ✓ Performance Knowledge P4 P4: Replanned staff areas to improve spatial relationships, circulation, and functional zoning. PD07 Establish project design goals. ✓ Performance Knowledge P3, P4, P5 P3: Developed design responses based on the project requirements and client comments. P4: Adjusted the staff-area design according to client requirements. P5: Developed the interior design concept based on the project objectives. PD08 Consider recommendations from geotechnical studies when establishing design parameters. ✗ Performance Knowledge - PD09 Assist the client in preparing the building program, including the list of spaces and their characteristics. ✗ Performance Knowledge - PD10 Gather information about the client’s vision, goals, budget, and schedule to validate the project scope and program. ✓ Performance Knowledge P4, P5 P4: Reviewed and implemented client comments for staff-area re-planning. P5: Used project requirements to develop the proposed office layout and interior design concept. PD11 Assess the environmental impact to formulate design decisions. ✗ Performance Knowledge - PD12 Review legal documents related to the site to determine project constraints. ✓ Performance Knowledge P2 Used the reviewed legal requirements to understand and define the constraints affecting the project design. Completed : 46.67% 7+8=15 7 0 Chapter 2 PROJECT PLANNING & CONCEPTUAL DESIGN 2.1 RELATED PROJECTS : I will use the Project No. listed in the table below as a reference for each competency. For more details on how each competency was achieved, please refer to the corresponding monthly reports submitted with this NOS report. Project name Project No. Al hashemiya vocational school for boys P1 Dubai Bay Island - island B P2 Tuaja Al Madinah P3 VOCO hotel P4 AJWE Building P5 2.2 COMPETENCY ACHIEVEMENT
OIP-02-02, Rev.1.0 NOS Report Form Level of achievement of the required Programming and Analysis competencies during the internship period. Competencies Details Cover age Status Category Related project NO. How the Competency Was Achieved No. Competency CD01 Perform building code analysis. ✓ Performance Knowledge P3, P4,P2 P2: Reviewed zoning laws, building codes, and permit requirements. P3: Applied building code requirements during the design development. P4: Adjusted the layout based on project requirements, including the male/female ratio. CD02 Define requirements for site survey based on the established project scope. ✗ Performance Knowledge - CD03 Select materials, finishes, and systems based on technical properties and aesthetic requirements. ✓ Performance Knowledge P5 P5: Prepared mood boards by selecting materials, finishes, and colour palettes for the office redesign. CD04 Determine human comfort levels and corresponding design parameters for building engineering systems. ✓ Performance Knowledge P4 P4: Relocated toilets internally to reduce humidity impact and improve the space conditions. CD05 Prepare conceptual design alternatives for client review. ✓ Performance Knowledge P3, P4, P5 P3: Developed design responses based on client comments. P4: Proposed solutions for the staff-area re-planning. P5: Developed alternative interior design solutions for the office layout. CD06 Perform massing and volumetric studies. ✓ Performance Knowledge P2 P2: Converted regulations into diagrams and developed a massing study to test development limits on the site. CD07 Prepare Cost of Work estimates. ✗ Performance Knowledge - CD08 Apply principles of historic preservation for projects involving building restoration or renovation. ✗ Performance Knowledge - CD09 Apply understanding of evolving sustainable design strategies and technologies, as well as green building rating systems. ✗ Performance Knowledge - CD10 Design landscape elements for the site. ✗ Performance Knowledge - CD11 Convert sketches into technical drawings. ✓ Performance Knowledge P3 P3: Converted design information into technical drawings to communicate the proposed design. CD12 Present conceptual design ideas orally. ✓ Performance Knowledge P5 P5: Presented the proposed interior design concept and spatial solutions. CD13 Communicate design ideas graphically. ✓ Performance Knowledge P5 P5: Prepared mood boards, light renderings, and a PowerPoint presentation to communicate the design concept. CD13- 01 Communicate design ideas using hand drawings. ✗ Performance Knowledge - CD13- 02 Communicate design ideas using two-dimensional (2D) computer- aided design software. ✓ Performance Knowledge P2,P5 P2: Used 2D drawings and diagrams to communicate site and regulatory studies. P5: Developed 2D visualizations of the proposed office layout. CD13- 03 Communicate design ideas using three-dimensional (3D) computer- aided design software. ✓ Performance Knowledge P2, P3, P5 P2: Used 3D massing studies to communicate site development options. P3: Used 3D software to communicate design proposals. P5: Produced 3D visualizations/renderings of the interior design. CD13- 04 Communicate design ideas using BIM software. ✓ Performance Knowledge P1 P1: Prepared architectural drawings for three floors, including dimensions, door tags, and window tags, using BIM software. Completed : 64.7% 11+6=1 7 11 0
OIP-02-02, Rev.1.0 NOS Report Form Chapter 3 DESIGN DEVELOPMENT, DETAILED DESIGN AND CONSTRUCTION INFORMATION 3.1 RELATED PROJECTS : I will use the Project No. listed in the table below as a reference for each competency. For more details on how each competency was achieved, please refer to the corresponding monthly reports submitted with this NOS report. Project name Project No. Al hashemiya vocational school for boys P1 Dubai Bay Island - island B P2 Tuaja Al Madinah P3 VOCO hotel P4 AJWE Building P5 3.2 COMPETENCY ACHIEVEMENT Level of achievement of the required Programming and Analysis competencies during the internship period. Competencies Details Coverage Status Category Related project NO. How the Competency Was Achieved No. Competency DD01 Coordinate design work of consultants. ✓ Performance Knowledge P4 P4: Coordinated the proposed column relocation with the structural team. DD02 Coordinate design work of in- house team members. ✗ Performance Knowledge - DD03 Prepare submittals for regulatory approval. ✗ Performance Knowledge - DD04 Source and research suppliers. ✗ Performance Knowledge - DD05 Select furniture, fixtures, and equipment that meet the client’s design requirements and needs. ✗ Performance Knowledge - DD06 Apply knowledge in construction technology. ✗ Performance Knowledge - DD06- 01 Apply knowledge of construction systems. ✗ Performance Knowledge - DD06- 02 Apply knowledge of construction materials. ✗ Performance Knowledge - DD06- 03 Apply knowledge of construction processes. ✗ Performance Knowledge - DD07 Develop and integrate building systems design solutions. ✓ Performance Knowledge - P4: Integrated circulation and housekeeping zones while considering structural constraints.
OIP-02-02, Rev.1.0 NOS Report Form DD07- 01 Develop and integrate heating, ventilation, and air- conditioning systems. ✗ Performance Knowledge - DD07- 02 Develop and integrate plumbing and sanitary systems. ✗ Performance Knowledge - DD07- 03 Develop and integrate lighting design. ✗ Performance Knowledge - DD07- 04 Develop and integrate acoustic design. ✗ Performance Knowledge - DD08 Advance green building elements. ✗ Performance Knowledge - DD08- 01 Develop low-impact social, environmental, and economic design solutions. ✗ Performance Knowledge - DD08- 02 Apply knowledge of materials and technologies specific to sustainable design. ✗ Performance Knowledge - DD08- 03 Apply principles of climate- responsive design. ✗ Performance Knowledge - DD08- 04 Enhance energy efficiency. ✗ Performance Knowledge - DD08- 05 Apply certification systems. ✗ Performance Knowledge - DD09 Put together construction information packages. ✗ Performance Knowledge - DD09- 01 Develop construction drawings, including plans, sections, elevations, wall sections, details, and schedules. ✓ Performance Knowledge P1 P1: Prepared architectural annotations for three floors, including dimensions, door tags, and window tags. DD09- 02 Survey quantities to prepare Bills of Quantities. ✗ Performance Knowledge - DD09- 03 Develop project specifications. ✗ Performance Knowledge - DD10 Review and comply with building codes, including fire safety and accessibility requirements. ✗ Performance Knowledge -- DD11 Contribute to Building Information Modelling. ✗ Performance Knowledge - DD11- 01 Build digital models using BIM modelling software. ✗ Performance Knowledge - DD11- 02 Develop or reinforce the transition to BIM. ✗ Performance Knowledge - DD11- 03 Manage BIM operations. ✗ Performance Knowledge - Completed : 10.34% 3+26=29 3 0 -
OIP-02-03, Rev.1.0 Final Report 2ND MONTH REPORT 15/3/2026-15/4/2026
Email 22110059@htu.edu.jo Phone 0799864046 Address Amman Apprenticeship ReportSchool of Built Environment Engineering Apprenticeship Monthly Report Student Name: Farah Abuzaid Student ID: 22110059 Major: Architectural Engineering Apprenticeship Mentor:Arch. Jomana Alawi Company Name: AJi group Industry Mentor: Eng . Hamza Bustanji Date of Report:2/15/2026 Report Type: Second Monthly Report Dates: 315/2025 – 4/16/2025
Table of Contents I. Apprenticeship Monthly Report ........................................................................1 II. General Introduction ..........................................................................................1 A. General Company Overview ........................................................................................... 1 B. Apprenticeship Duration and Phase Progression ......................................................... 1 III. Section 1: Office Work (Design Phases) ............................................................1 Project 1 ......................................................................................................................................... 1 Task 1 :............................................................................................................................................ 1 Task 2 :............................................................................................................................................ 2 IV. Project 2 ...............................................................................................................4 Task 1 :............................................................................................................................................ 4 Task 2 :............................................................................................ Error! Bookmark not defined. V. Project 3 ...............................................................................................................5 Task 1 :............................................................................................................................................ 5 Task 2 :............................................................................................................................................ 5 VI. Project 4 ............................................................... Error! Bookmark not defined. Task 1 :............................................................................................ Error! Bookmark not defined. Task 2 :............................................................................................ Error! Bookmark not defined. VII. List of Achieved Competencies ......................... Error! Bookmark not defined. VIII. Section 2 : Site Supervision ...............................................................................9 IX. Section 3 : Project Management...................................................................... 10 X. Section 4: Executive Summary ........................................................................ 10 XI. Appendices........................................................................................................ 15
Farah’s Monthly Report PG. 1OIP-02-01, Rev.1.0 General Introduction A. General Company Overview B. Apprenticeship Duration and Phase Progression Section 1: Office Work (Design Phases) Project 1 Project Name: AJWE Building Project Location: Jordan – Amman Project Phase: Design Development Description of Project : The project involves the interior redesign and spatial reorganization of the AJWE Department offices. The primary goal is to enhance the office environment and workflow by replanning the interior layouts and updating the color schemes and materials to create a more productive and professional atmosphere. Task 1 : Lightening design ceiling for two offices Detailed Program
Farah’s Monthly Report PG. 2OIP-02-01, Rev.1.0 Task 2 : 3d shots for the office Task 3 : choosing office furniture material and tiles material Task 4 : furniture materials and reflet it to 3d shots
Farah’s Monthly Report PG. 3OIP-02-01, Rev.1.0 Task 5 : making sure about the as built drawing and make survey for the first floor and the 4th floor List of Achieved Competencies: Code Competency Description How? Type CD03 Select materials, finishes, and systems based on technical properties and aesthetic requirements Selected furniture materials, tiles, and finishes for office interior design Chose office furniture and ensured it meets functional and aesthetic requirements. Performance DD07-03 Lighting design Designed ceiling lighting layout for office spaces Performance
Farah’s Monthly Report PG. 4OIP-02-01, Rev.1.0 CD13-03 Communicate design ideas with three-dimensional (3-D) computer aided design software Produced 3D shots and applied materials to visualize the design Performance DD06-02 Construction materials Reviewed and applied knowledge of materials during selection process Knowledge PD02-01 Prepare site analysis diagrams to document existing conditions, features, infrastructure, and regulatory requirements Verified as-built drawings and conducted site survey Preformance Project 2 Project Name: NOBLES | ABDOUN PEARL Project Location: Abdoun, Amman, Jordan Project Phase: Design Development Description of Project: Task 1 : Attending the meeting with client ✓ By teams link Task 2 : write the client notes and modifications assigned List of Achieved Competencies:
Farah’s Monthly Report PG. 5OIP-02-01, Rev.1.0 Code Competency Description How? Type PM01 Participate in pre-construction, pre- installation, and regular progress meetings with design team Attended client meeting and participated in project discussion Performance PM03 Collaborate with stakeholders during design process to maintain design intent and comply with owner specifications Understood client requirements and coordinated modifications Performance PM07 Prepare written communications related to design ideas, project documentation, and contracts Documented client notes and design changes Performance Project 3 Project Name: VOCO Hotel Project Location: Aqaba , Jordan Project Phase: Construction Documentation Description of Project: Task 1 : change links in rivet for the hotel rooms Task 2 :change the rooms name according to the new room matrix excel file Task 3 :sheets new room legend Task 4 :the output in pdf format List of Achieved Competencies: Code Competency Description How? Type DD11 Contribute to Building Information Modelling (BIM) Worked on Revit model by updating links and room data Preformance
Farah’s Monthly Report PG. 6OIP-02-01, Rev.1.0 DD11-01 Build digital models using BIM modelling software Modified room names and coordinated model elements Preformance DD09 Put together construction information packages Prepared room legend and organized drawing outputs Preformance DD09-01 Develop construction drawings (plans, sections, elevations, wall sections, details, schedules) Produced documentation sheets and exported them as PDF Preformance CD13-04 Communicate design ideas with BIM software Used Revit to represent updated room data and layouts Preformance Project 4 Project Name: Masar Project Location: Project Phase: Design Development Description of Project: Task 1 : reading the guidelines from KSA for the render materials
Farah’s Monthly Report PG. 7OIP-02-01, Rev.1.0 Task 2 : Prepare the skp file to make the renders by Lumion List of Achieved Competencies: Code Competency Description How? Type DD06-02 Construction materials Reviewed KSA guidelines for rendering materials Knowledge CD13-03 Communicate design ideas with three-dimensional (3-D) computer aided design software Prepared SketchUp model for rendering in Lumion Preformance Project 5 Project Name: Aleyon Oasis , واحة العيون Project Location: KSA Project Phase: Conceptual Design Description of Project:
Farah’s Monthly Report PG. 8OIP-02-01, Rev.1.0 Task 1 : Site Analysis 15/4/2026 Task 2 : Site Analysis update 16/4/2026 The task : make the colors like this one The task done and delivered to Eng. Hamza in PSD format List of Achieved Competencies: Code Competency Description How? Type PD02 Perform Site analysis (Context, climate, approach and access, environment, views, solar access, noise, etc.) Conducted full site analysis for the project Preformance
Farah’s Monthly Report PG. 9OIP-02-01, Rev.1.0 PD02-01 Prepare site analysis diagrams to document existing conditions, features, infrastructure, and Created and updated site analysis diagrams using Photoshop Preformance CD13-02 Communicate design ideas with two-dimensional (2-D) computer aided design software Produced diagrams and visual presentations in PSD format Preformance Section 2 : Site Supervision Project 1 Project Name: Holiday Inn resort Project Location: Dead see, Jordan Project Phase: Choose an item. Description of Project: Task 1 : On site Meeting ( writing notes )
Farah’s Monthly Report PG. 10OIP-02-01, Rev.1.0 Task 2 : activities ( tiles demolishing – furniture ) List of Achieved Competencies: Code Competency Description How? Type S01 Review shop drawings and submittals during construction for conformance with design intent Observed construction activities and compared them with design intent Preformance S03 Complete field reports to document field observations from construction site visits Recorded site meeting notes and documented observations Preformance Section 3 : Project Management Section 4: Executive Summary 1. Any problems / Challenges and how did you overcome them? 2. Any training courses you attended during the apprenticeship, whether you opted for independently or through the employer. • Name of the course • Main Topics
Farah’s Monthly Report PG. 11OIP-02-01, Rev.1.0 • Certificate (Include merged file in appendices or attach a copy) 3. Technical and non-technical skills • Technical • Non Technical 4. Did you work on the competencies: ▪ Over-All Achieved Competencies: Code Competency Name Project No. Type PD02 Perform Site analysis (Context, climate, approach and access, environment, views, solar access, noise, etc.) Project 5 Performance PD02-01 Prepare site analysis diagrams to document existing conditions, features, infrastructure, and regulatory requirements Project 5, 1 Performance CD03 Select materials, finishes, and systems based on technical properties and aesthetic requirements Project 1 Performance CD13-02 Communicate design ideas with two- dimensional (2-D) computer aided design software Project 5 Performance CD13-03 Communicate design ideas with three- dimensional (3-D) computer aided design software Projects 1, 4 Performance CD13-04 Communicate design ideas with BIM software Project 3 Performance DD05 Select furniture, fixtures, and equipment that meet client’s design requirements and needs Project 1 Performance DD06-02 Construction materials Projects 1, 4 Knowledge DD07-03 Lighting design Project 1 Performance DD09 Put together construction information packages Project 3 Performance
Farah’s Monthly Report PG. 12OIP-02-01, Rev.1.0 DD09-01 Develop construction drawings (plans, sections, elevations, wall sections, details, schedules) Project 3 Performance DD11 Contribute to Building Information Modelling (BIM) Project 3 Performance DD11-01 Build digital models using BIM modelling software Project 3 Performance PM01 Participate in pre-construction, pre- installation, and regular progress meetings with design team Project 2 Performance PM03 Collaborate with stakeholders during design process to maintain design intent and comply with owner specifications Project 2 Performance PM07 Prepare written communications related to design ideas, project documentation, and contracts Project 2 Performance S01 Review shop drawings and submittals during construction for conformance with design intent Site Project Performance S03 Complete field reports to document field observations from construction site visits Site Project Performance
Farah’s Monthly Report PG. 13OIP-02-01, Rev.1.0
Farah’s Monthly Report PG. 14OIP-02-01, Rev.1.0
Farah’s Monthly Report PG. 15OIP-02-01, Rev.1.0 5. Any Events / Conferences you participated 6. Your Plan for Next Month. This plan to cover the Site Supervision Competencies Appendices Training Plan • Monthly Attendance Sheet
Month: Two / 15 Mar Date Day Time In Time Out Total Hours Apprentice Signature 1 17/3/2026 Tuesday 9:30 AM 5:00 PM 7.5 hrs 2 18/3/2026 Wednesday 3 19/3/2026 Thursday 6 20/3/2026 Friday 7 21/3/2026 Saturday 8 22/3/2026 Sunday 9 23/3/2026 Monday 10 24/3/2026 Tuesday 9:30 AM 4:00 PM 6.5 hrs 11 25/3/2026 Wednesday 9:30 AM 5:30 PM 8 hrs 12 26/3/2026 Thursday 13 27/3/2026 Friday 14 28/3/2026 Saturday 15 29/3/2026 Sunday 9:30 AM 5:30 PM 8 hrs 16 30/3/206 Monday 12:00 PM 5:30 PM 5.5 hrs 17 31/3/2026 Tuesday 9:30 AM 5:30 PM 8 hrs 18 1/4/2026 Wednesday 9:30 AM 6:30 PM 9 hrs 19 2/4/2026 Thursday 8:30 AM 5:00 PM 8.5 hrs 20 3/4/2026 Friday 21 4/4/2026 Saturday 22 5/4/2026 Sunday 9:30 AM 6:30 PM 9 hrs 23 6/4/2026 Monday 24 7/4/2026 Tuesday 8:30 AM 5:30 PM 8.5 hrs 25 8/4/2026 Wednesday 10:00 AM 5:30 PM 7.5 hrs 26 9/4/2026 Thursday 12:30 AM 5:00 PM 4.5 hrs 27 10/4/2026 Friday 28 11/4/2026 Saturday 29 12/4/2026 Sunday 8:30 AM 5:30 PM 8 hrs 30 13/4/2026 Monday 9:30 AM 5:30 PM 7 hrs 31 14/4/2026 Tuesday 10:00 AM 4:00 PM 6 hrs 32 15/4/2026 Wednesday 9:00 AM 5:00 PM 7 hrs 32 16/4/2026 Thursday 9:00 AM 5:00 PM 7 hrs Attendance Total 27 AJi group Workplace mentor: Eng . Hamza Bustanji Workplace mentor Signature: Daily Apprenticeship Attendance Sheet Apprentice Name: Farah Abuzaid Workplace Name:
OIP-02-02, Rev.1.0 NOS Report Form NOS REPORT MONTH 2 STUDENT NAME: FARAH ABUZAID COMPANY: AJI GROUP Chapter Name of NOS: Number of NOS: 1 Programming & Analysis (Pre Design Phase) 2 2 Project Planning & Conceptual Design 4 3 Design Development, Detailed Design and Construction Informtion 7 4 Project Management 3 5 Supervision 2 6 Construction Management 4 **Performance criteria of the NOS and how you applied it in your company ** Include all the Competencies (Code/The Competency/How you applied it) (Explain and include evidence from your work)
OIP-02-02, Rev.1.0 NOS Report Form Chapter 1 PROGRAMMING & ANALYSIS (PRE DESIGN PHASE) 1.1 RELATED PROJECTS : I will use the Project No. listed in the table below as a reference for each competency. For more details on how each competency was achieved, please refer to the corresponding monthly reports submitted with this NOS report. Project name Project No. AJWE Building P1 Nobles | Abdoun Pearl P2 VOCO Hotel P3 Masar P4 Aleyon Oasis P5 1.2 COMPETENCY ACHIEVEMENT Competencies Details Coverage Status Category Related project NO. How the Competency Was Achieved No. Competency PD01 Determine the impact of applicable zoning and development ordinances to identify project constraints. ✗ Performance Knowledge ----- --------------------- PD02 Perform site analysis, including context, climate, approach and access, environment, views, solar access, noise, and other relevant factors. ✓ Performance Knowledge P5 P5 – Aleyon Oasis: Conducted a full site analysis for the project. PD02- 01 Prepare site analysis diagrams to document existing conditions, site features, infrastructure, and regulatory requirements. ✓ Performance Knowledge P5 P5 – Aleyon Oasis: Created and updated site analysis diagrams using Photoshop. P1 – AJWE Building: Verified as-built drawings and conducted a site survey for the 1st and 4th floors. PD02- 02 Evaluate the opportunities and constraints of alternative sites. ✗ Performance Knowledge ----- --------------------- PD02- 03 Determine the impact of environmental, zoning, and other regulations on the site. ✗ Performance Knowledge ----- --------------------- PD03 Evaluate the results of feasibility studies to determine the project’s financial viability. ✗ Performance Knowledge ----- ---------------------
OIP-02-02, Rev.1.0 NOS Report Form PD04 Establish sustainability goals affecting building performance. ✗ Performance Knowledge ----- --------------------- PD05 Apply a checklist of potential strategies with reference to green building rating systems. ✗ Performance Knowledge ----- --------------------- PD06 Prepare diagrams illustrating spatial relationships and functional adjacencies. ✗ Performance Knowledge P4: Replanned staff areas to improve spatial relationships, circulation, and functional zoning. PD07 Establish project design goals. ✗ Performance Knowledge P3: Developed design responses based on the project requirements and client comments. P4: Adjusted the staff-area design according to client requirements. P5: Developed the interior design concept based on the project objectives. PD08 Consider recommendations from geotechnical studies when establishing design parameters. ✗ Performance Knowledge ----- --------------------- PD09 Assist the client in preparing the building program, including the list of spaces and their characteristics. ✗ Performance Knowledge ----- --------------------- PD10 Gather information about the client’s vision, goals, budget, and schedule to validate the project scope and program. ✗ Performance Knowledge P4: Reviewed and implemented client comments for staff-area re-planning. P5: Used project requirements to develop the proposed office layout and interior design concept. PD11 Assess the environmental impact to formulate design decisions. ✗ Performance Knowledge PD12 Review legal documents related to the site to determine project constraints. ✗ Performance Knowledge Used the reviewed legal requirements to understand and define the constraints affecting the project design. Completed : 12.5%% 2+13=61 2 0 Chapter 2 PROJECT PLANNING & CONCEPTUAL DESIGN 2.1 RELATED PROJECTS : I will use the Project No. listed in the table below as a reference for each competency. For more details on how each competency was achieved, please refer to the corresponding monthly reports submitted with this NOS report. Project name Project No. AJWE Building P1 Nobles | Abdoun Pearl P2 VOCO Hotel P3 Masar P4 Aleyon Oasis P5
OIP-02-02, Rev.1.0 NOS Report Form 2.2 COMPETENCY ACHIEVEMENT Level of achievement of the required Programming and Analysis competencies during the internship period. Competencies Details Covera ge Status Category Relate d project NO. How the Competency Was Achieved No. Competency CD01 Perform building code analysis. ✗ Performance Knowledge ----- --------------------- CD02 Define requirements for site survey based on the established project scope. ✗ Performance Knowledge ----- --------------------- CD03 Select materials, finishes, and systems based on technical properties and aesthetic requirements. ✓ Performance Knowledge P1 P1 – AJWE Building: Selected furniture materials, tile materials, and finishes for the office interior design. CD04 Determine human comfort levels and corresponding design parameters for building engineering systems. ✗ Performance Knowledge ----- --------------------- CD05 Prepare conceptual design alternatives for client review. ✗ Performance Knowledge ----- --------------------- CD06 Perform massing and volumetric studies. ✗ Performance Knowledge ----- --------------------- CD07 Prepare Cost of Work estimates. ✗ Performance Knowledge ----- --------------------- CD08 Apply principles of historic preservation for projects involving building restoration or renovation. ✗ Performance Knowledge ----- --------------------- CD09 Apply understanding of evolving sustainable design strategies and technologies, as well as green building rating systems. ✗ Performance Knowledge ----- --------------------- CD10 Design landscape elements for the site. ✗ Performance Knowledge ----- --------------------- CD11 Convert sketches into technical drawings. ✗ Performance Knowledge ----- --------------------- CD12 Present conceptual design ideas orally. ✗ Performance Knowledge ----- --------------------- CD13 Communicate design ideas graphically. ✗ Performance Knowledge ----- --------------------- CD13- 01 Communicate design ideas using hand drawings. ✗ Performance Knowledge ----- --------------------- CD13- 02 Communicate design ideas using two-dimensional (2D) computer- aided design software. ✓ Performance Knowledge P5 P5 – Aleyon Oasis: Produced site analysis diagrams and visual presentations in PSD format. CD13- 03 Communicate design ideas using three-dimensional (3D) computer- aided design software. ✓ Performance Knowledge P1-P4 P1 – AJWE Building: Produced 3D office shots and applied selected materials. P4 – Masar: Prepared the SketchUp model for rendering in Lumion. CD13- 04 Communicate design ideas using BIM software. ✓ Performance Knowledge P3 P3 – VOCO Hotel: Used Revit to update room data and layouts. Completed : 23.5% 4+13=17 4 0
OIP-02-02, Rev.1.0 NOS Report Form Chapter 3 DESIGN DEVELOPMENT, DETAILED DESIGN AND CONSTRUCTION INFORMATION 3.1 RELATED PROJECTS : I will use the Project No. listed in the table below as a reference for each competency. For more details on how each competency was achieved, please refer to the corresponding monthly reports submitted with this NOS report. Project name Project No. AJWE Building P1 Nobles | Abdoun Pearl P2 VOCO Hotel P3 Masar P4 Aleyon Oasis P5 3.2 COMPETENCY ACHIEVEMENT Level of achievement of the required Programming and Analysis competencies during the internship period. Competencies Details Coverage Status Category Related project NO. How the Competency Was Achieved No. Competency DD01 Coordinate design work of consultants. ✗ Performance Knowledge ----- --------------------- DD02 Coordinate design work of in- house team members. ✗ Performance Knowledge ----- --------------------- DD03 Prepare submittals for regulatory approval. ✗ Performance Knowledge ----- --------------------- DD04 Source and research suppliers. ✗ Performance Knowledge ----- --------------------- DD05 Select furniture, fixtures, and equipment that meet the client’s design requirements and needs. ✓ Performance Knowledge P1 P1 – AJWE Building: Selected office furniture materials and applied the selected furniture materials to the 3D shots. DD06 Apply knowledge in construction technology. ✗ Performance Knowledge ----- --------------------- DD06- 01 Apply knowledge of construction systems. ✗ Performance Knowledge ----- --------------------- DD06- 02 Apply knowledge of construction materials. ✓ Performance Knowledge P1,P4 P1 – AJWE Building: Reviewed material knowledge during the furniture and tile material selection process. P4 – Masar: Reviewed KSA guidelines for rendering materials.
OIP-02-02, Rev.1.0 NOS Report Form DD06- 03 Apply knowledge of construction processes. ✗ Performance Knowledge ----- --------------------- DD07 Develop and integrate building systems design solutions. ✗ Performance Knowledge ----- --------------------- DD07- 01 Develop and integrate heating, ventilation, and air- conditioning systems. ✗ Performance Knowledge ----- --------------------- DD07- 02 Develop and integrate plumbing and sanitary systems. ✗ Performance Knowledge ----- --------------------- DD07- 03 Develop and integrate lighting design. ✓ Performance Knowledge P1 P1 – AJWE Building: Designed the ceiling lighting layout for two offices. DD07- 04 Develop and integrate acoustic design. ✗ Performance Knowledge ----- --------------------- DD08 Advance green building elements. ✗ Performance Knowledge ----- --------------------- DD08- 01 Develop low-impact social, environmental, and economic design solutions. ✗ Performance Knowledge ----- --------------------- DD08- 02 Apply knowledge of materials and technologies specific to sustainable design. ✗ Performance Knowledge ----- --------------------- DD08- 03 Apply principles of climate- responsive design. ✗ Performance Knowledge ----- --------------------- DD08- 04 Enhance energy efficiency. ✗ Performance Knowledge ----- --------------------- DD08- 05 Apply certification systems. ✗ Performance Knowledge ----- --------------------- DD09 Put together construction information packages. ✓ Performance Knowledge P3 P3 – VOCO Hotel: Prepared the new room legend and organized the drawing outputs. DD09- 01 Develop construction drawings, including plans, sections, elevations, wall sections, details, and schedules. ✓ Performance Knowledge P3 P3 – VOCO Hotel: Produced documentation sheets and exported the updated drawings in PDF format. DD09- 02 Survey quantities to prepare Bills of Quantities. ✗ Performance Knowledge ----- --------------------- DD09- 03 Develop project specifications. ✗ Performance Knowledge ----- --------------------- DD10 Review and comply with building codes, including fire safety and accessibility requirements. ✗ Performance Knowledge ----- --------------------- DD11 Contribute to Building Information Modelling. ✓ Performance Knowledge P3 P3 – VOCO Hotel: Worked on the Revit model by updating links and room data. DD11- 01 Build digital models using BIM modelling software. ✓ Performance Knowledge P3 P3 – VOCO Hotel: Modified room names and coordinated model elements in Revit. DD11- 02 Develop or reinforce the transition to BIM. ✗ Performance Knowledge ----- --------------------- DD11- 03 Manage BIM operations. ✗ Performance Knowledge ----- --------------------- Completed : 24.1% 7+22=29 0 0
OIP-02-02, Rev.1.0 NOS Report Form Chapter 4 PROJECT MANAGEMENT 4.1 RELATED PROJECTS I will use the Project No. listed in the table below as a reference for each competency. For more details on how each competency was achieved, please refer to the corresponding monthly reports submitted with this NOS report. Project name Project No. Al hashemiya vocational school for boys P1 Dubai Bay Island - island B P2 Tuaja Al Madinah P3 VOCO hotel P4 AJWE Building P5 4.2 COMPETENCY ACHIEVEMENT Level of achievement of the required Programming and Analysis competencies during the internship period. Competencies Details Coverage Status Category Related project NO. How the Competency Was Achieved No. Competency PM01 Participate in pre- construction, pre-installation, and regular progress meetings with the design team. ✓ Performance Knowledge P2 Task 1: Attended the client meeting via Teams and participated in the project discussion. PM02 Determine the design fee budget. ✗ Performance Knowledge ----- --------------------- PM03 Collaborate with stakeholders during the design process to maintain design intent and comply with the owner’s specifications. ✓ Performance Knowledge P2 Task 2: Reviewed the client notes and coordinated the assigned design modifications. PM04 Determine the project schedule. ✗ Performance Knowledge ----- --------------------- PM05 Understand the implications of project delivery methods. ✗ Performance Knowledge ----- --------------------- PM06 Prepare the Architect– Consultant Agreement. ✗ Performance Knowledge ----- --------------------- PM07 Prepare written communications related to design ideas, project documentation, and contracts. ✓ Performance Knowledge P2 Task 2: Recorded the client notes and documented the assigned design modifications. PM08 Assist the client in determining the delivery method for construction of the project. ✗ Performance Knowledge ----- ---------------------
OIP-02-02, Rev.1.0 NOS Report Form PM09 Maintain compliance with established milestones. ✗ Performance Knowledge ----- --------------------- PM10 Prepare the Owner–Architect Agreement. ✗ Performance Knowledge ----- --------------------- PM11 Assist the owner in obtaining the necessary permits and approvals. ✗ Performance Knowledge ----- --------------------- PM12 Perform a constructability review to determine the buildability, bidability, and construction sequencing of the proposed project. ✗ Performance Knowledge ----- --------------------- PM13 Conduct periodic progress meetings with the design and project team. ✗ Performance Knowledge ----- --------------------- PM14 Establish methods for Architect–Client communication based on the project scope of work. ✗ Performance Knowledge ----- --------------------- PM15 Identify changes in project scope that require additional services. ✗ Performance Knowledge ----- --------------------- PM16 Manage modifications to the construction contract. ✗ Performance Knowledge ----- --------------------- PM17 Manage information exchange during construction. ✗ Performance Knowledge ----- --------------------- PM18 Perform constructability reviews throughout the design process. ✗ Performance Knowledge ----- --------------------- PM19 Perform quality-control reviews throughout the documentation process. ✗ Performance Knowledge ----- --------------------- PM20 Define the roles and responsibilities of team members. ✗ Performance Knowledge ----- --------------------- PM21 Determine the scope of services. ✗ Performance Knowledge ----- --------------------- PM22 Manage the project-specific bidding process. ✗ Performance Knowledge ----- --------------------- PM23 Monitor the performance of design-team consultants. ✗ Performance Knowledge ----- --------------------- PM24 Evaluate the appropriateness of Building Information Modelling for the proposed project. ✗ Performance Knowledge ----- --------------------- PM25 Present the design concept to stakeholders. ✗ Performance Knowledge ----- --------------------- PM26 Resolve conflicts that may arise during the design and construction processes. ✗ Performance Knowledge ----- --------------------- PM27 Prepare a staffing plan to meet project goals. ✗ Performance Knowledge ----- --------------------- PM28 Manage the implementation of sustainability criteria. ✗ Performance Knowledge ----- ---------------------
OIP-02-02, Rev.1.0 NOS Report Form PM29 Assist the client in selecting contractors. ✗ Performance Knowledge ----- --------------------- PM30 Put together technical and financial offers. ✗ Performance Knowledge ----- --------------------- Completed : 10% 3+27=03 0 0 Chapter 5 SUPERVISION 5.1 RELATED PROJECTS I will use the Project No. listed in the table below as a reference for each competency. For more details on how each competency was achieved, please refer to the corresponding monthly reports submitted with this NOS report. Project name Project No. Site Project – Holiday Inn Resort S/P1 5.2 COMPETENCY ACHIEVEMENT Level of achievement of the required Programming and Analysis competencies during the internship period. Competencies Details Coverage Status Category Related project NO. How the Competency Was Achieved No. Competency S01 Review shop drawings and submittals during construction for conformance with design intent. ✓ Performance Knowledge S/P1 Site Project – Holiday Inn Resort: Observed tile demolition and furniture activities and compared the construction activities with the design intent. S02 Respond to Contractor Requests for Information. ✗ Performance Knowledge S03 Complete field reports to document field observations from construction site visits. ✓ Performance Knowledge S/P1 Site Project – Holiday Inn Resort: Recorded site meeting notes and documented observations during the site visit. S04 Review results from field reports, third-party inspections, and other test results for conformance with contract documents. ✗ Performance Knowledge ----- --------------------- S05 Review Applications and Certificates for Payment. ✗ Performance Knowledge ----- --------------------- S06 Manage project close-out procedures and documentation. ✗ Performance Knowledge ----- --------------------- S07 Inspection and approval of construction works. ✗ Performance Knowledge ----- ---------------------
OIP-02-02, Rev.1.0 NOS Report Form S07-01 Surveying works, including site boundaries and street alignment. ✗ Performance Knowledge ----- --------------------- S07-02 Excavation works. ✗ Performance Knowledge ----- --------------------- S07-03 Chain works. ✗ Performance Knowledge ----- --------------------- S07-04 Scaffolding works for footings. ✗ Performance Knowledge ----- --------------------- S07-05 Footing reinforcement. ✗ Performance Knowledge ----- --------------------- S07-06 Concrete works and tests. ✗ Performance Knowledge ----- --------------------- S07-07 Scaffolding works for columns. ✗ Performance Knowledge ----- --------------------- S07-08 Reinforcement works in columns and walls. ✗ Performance Knowledge ----- --------------------- S07-09 Scaffolding works for slabs. ✗ Performance Knowledge ----- --------------------- S07-10 Reinforcement works for slabs. ✗ Performance Knowledge ----- --------------------- S07-11 Concrete works for slabs and concrete tests. ✗ Performance Knowledge ----- --------------------- S07-12 Sand and aggregates. ✗ Performance Knowledge ----- --------------------- S07-13 Block concrete works. ✗ Performance Knowledge ----- --------------------- S07-14 Stone works. ✗ Performance Knowledge ----- --------------------- S07-15 Pointing. ✗ Performance Knowledge ----- --------------------- S07-16 Plastering. ✗ Performance Knowledge ----- --------------------- S07-17 Electrical conduits in slabs. ✗ Performance Knowledge ----- --------------------- S07-18 Electrical conduits in walls and floors. ✗ Performance Knowledge ----- --------------------- S07-19 Thermal insulation in slabs and walls. ✗ Performance Knowledge ----- --------------------- S07-20 Moisture insulation in roofs, floors, and walls. ✗ Performance Knowledge ----- --------------------- S07-21 Sanitary and mechanical works. ✗ Performance Knowledge ----- --------------------- S07-22 Flooring. ✗ Performance Knowledge ----- --------------------- S07-23 Wood works. ✗ Performance Knowledge ----- --------------------- S07-24 Metal works. ✗ Performance Knowledge ----- --------------------- S07-25 Painting. ✗ Performance Knowledge ----- --------------------- Completed : 6.25% 2+30=32 0 0
OIP-02-02, Rev.1.0 NOS Report Form Chapter 6 CONSTRUCTION MANAGEMENT 6.1 RELATED PROJECTS I will use the Project No. listed in the table below as a reference for each competency. For more details on how each competency was achieved, please refer to the corresponding monthly reports submitted with this NOS report. Project name Project No. Site Project – Holiday Inn Resort S/P1 6.2 COMPETENCY ACHIEVEMENT Level of achievement of the required Programming and Analysis competencies during the internship period. Competencies Details Coverage Status Category Related project NO. How the Competency Was Achieved No. Competency CM01 Prepare construction schedules. ✗ Performance Knowledge ----- --------------------- CM02 Prepare shop drawings. ✗ Performance Knowledge ----- --------------------- CM03 Prepare as-built drawings. ✗ Performance Knowledge ----- --------------------- CM04 Orchestrate the work of main contractors and subcontractors. ✗ Performance Knowledge ----- --------------------- CM05 Monitor and control construction works. ✓ Performance Knowledge S/P1 Observed the ongoing tile demolition and furniture works on site and compared the executed works with the design intent. CM05- 01 Refer to the list of construction works under Supervision — Inspection and Approval of Construction Works. ✓ Performance Knowledge S/P1 Attended a site meeting with the furniture and shelving suppliers and reviewed the proposed wood types, colours, and finishes to ensure they were in line with the project specifications. CM06 Prepare a staffing plan to meet project goals. ✗ Performance Knowledge ----- --------------------- CM07 Ensure the validity of construction insurance. ✗ Performance Knowledge ----- --------------------- CM08 Control and assure quality. ✓ Performance Knowledge S/P1 Participated in discussions with the suppliers to verify the wood material and colour selections against the required specifications and design intent. CM09 Ensure safety and security procedures are in place and followed. ✗ Performance Knowledge ----- --------------------- CM10 Resolve arising construction issues according to established procedures. ✓ Performance Knowledge S/P1 Requested information from the suppliers regarding the installation of concealed lighting within the wooden elements, to clarify the required installation method and ensure coordination with the design. Completed : 36.4% 4+7=11 0 4
OIP-02-03, Rev.1.0 Final Report 2ND MONTH REPORT 15/3/2026-15/4/2026 3RD MONTH REPORT 15/4/2026-15/5/2026
Email 22110059@htu.edu.jo Phone 0799864046 Address Amman Apprenticeship ReportSchool of Built Environment Engineering Apprenticeship Monthly Report Student Name: Farah Abuzaid Student ID: 22110059 Major: Architectural Engineering Apprenticeship Mentor:Arch. Jomana Alawi Company Name: AJi group Industry Mentor: Eng . Hamza Bustanji Date of Report:4/15/2026 Report Type: Third Monthly Report Dates: 4/15/2025 – 5/16/2025
Table of Contents I. Apprenticeship Monthly Report ........................................................................1 II. General Introduction ..........................................................................................1 III. Section 1: Office Work (Design Phases) ............................................................1 Project 1 ......................................................................................................................................... 1 Task 1 : : Massing .......................................................................................................................... 1 Task 2 : site section ...................................................................................................................... 2 Task 3 : Prepared the site plan layout for the project ................................................................ 2 Task 4 : Prepared case studies and analyzed reference projects. ........................................... 3 List of Achieved Competencies: ................................................................................................... 7 Project 2 ......................................................................................................................................... 7 Task 1 : Reviewed and studied the acoustic report for the VOCO Hotel project, gaining knowledge of acoustic design principles, sound insulation, reverberation control, HVAC noise management, acoustic standards, and construction detailing. ...................................... 7 Task 2 : Attended a technical workshop with ceiling suppliers to learn about acoustic ceiling systems, perforated panels, baffle ceilings, ceiling spans, lighting coordination, installation methods, and ceiling detailing applications. .......................................................... 8 List of Achieved Competencies: ................................................................................................... 9 IV. Section 2 : Site Supervision ...............................................................................9 V. Section 3 : Project Management........................................................................9 VI. Section 4: Executive Summary ..........................................................................9 VII. Appendices........................................................................................................ 10 • Training Plan ................................................................................................................... 10 • Monthly Attendance Sheet ............................................................................................ 10 • NOS report ...................................................................................................................... 10
Farah’s Monthly Report PG. 1OIP-02-01, Rev.1.0 General Introduction Section 1: Office Work (Design Phases) Project 1 Project Name: Aleyon Oasis , واحةالعيون Project Location: KSA Project Phase: Conceptual Design Description of Project: Task 1 : : Massing • Created site massing sketches. Detailed Program
Farah’s Monthly Report PG. 2OIP-02-01, Rev.1.0 • Produced a conceptual massing model for presentations. • Learned to use AI tools for architectural rendering and visualization. By Eng. Abdalla Task 2 : site section Task 3 : Prepared the site plan layout for the project ► reference
Farah’s Monthly Report PG. 3OIP-02-01, Rev.1.0 Option 1+ Option 2: Task 4 : Prepared case studies and analyzed reference projects. La Perla project
Farah’s Monthly Report PG. 4OIP-02-01, Rev.1.0 Task 5 : Prepared a conclusion and summary of the required tasks for the villas project Task 6: Designed the attached villa type
Farah’s Monthly Report PG. 5OIP-02-01, Rev.1.0 Task 7: Designed the attached villa type 3D
Farah’s Monthly Report PG. 6OIP-02-01, Rev.1.0
Farah’s Monthly Report PG. 7OIP-02-01, Rev.1.0 List of Achieved Competencies: Code Competency Description How? Type CD05 Prepare conceptual design alternatives for client review Prepared and compared different site layout and planning options (Option 1 and Option 2) to evaluate conceptual design alternatives. Performance CD13- 02 Communicate design ideas with two- dimensional (2-D) computer aided design software Prepared the architectural site plan layout and design drawings using AutoCAD. Performance CD11 Convert sketches into technical drawings Converted conceptual sketches and planning ideas into organized architectural drawings for the project. Performance PD07 Establish project design goals Developed the attached villa concept and design approach based on the project objectives and site conditions. Performance Project 2 Project Name: VOCO Hotle. Project Location: Jordan / Aqaba. Project Phase: Design Development Description of Project: Task 1 : Reviewed and studied the acoustic report for the VOCO Hotel project, gaining knowledge of acoustic design principles, sound insulation, reverberation control, HVAC noise management, acoustic standards, and construction detailing. Task Status: Review ► Topics Covered in the Acoustic Report
Farah’s Monthly Report PG. 8OIP-02-01, Rev.1.0 Task 2 : Attended a technical workshop with ceiling suppliers to learn about acoustic ceiling systems, perforated panels, baffle ceilings, ceiling spans, lighting coordination, installation methods, and ceiling detailing applications. ASG + Staitieh Group
Farah’s Monthly Report PG. 9OIP-02-01, Rev.1.0 List of Achieved Competencies: project 2 Code Competency Description How? Type DD07- 04 Acoustic design Reviewed the acoustic report to understand sound insulation, reverberation control, HVAC noise management, acoustic standards, and construction detailing requirements for hotel spaces. Knowledge DD06- 02 Construction materials Studied acoustic ceiling materials, perforated panels, baffle ceilings, and their technical performance during the supplier workshop. Knowledge DD07- 03 Lighting design Learned how lighting layouts are coordinated with acoustic ceiling systems and HVAC services to achieve both functional and acoustic performance. Knowledge DD04 Source/research suppliers Attended a technical workshop with USG and Estithiya suppliers to understand ceiling products, installation methods, spans, and manufacturer recommendations for architectural applications. Knowledge Section 2 : Site Supervision Section 3 : Project Management Section 4: Executive Summary 1. Any problems / Challenges and how did you overcome them? 2. Any training courses you attended during the apprenticeship, whether you opted for independently or through the employer. • Name of the course • Main Topics • Certificate (Include merged file in appendices or attach a copy) 3. Technical and non-technical skills
Farah’s Monthly Report PG. 10OIP-02-01, Rev.1.0 • Technical • Non-Technical 4. Did you work on the competencies: ▪ Over-All Achieved Competencies: Code Competency Name Project No. Type CD05 Prepare conceptual design alternatives for client review P1 Performance CD11 Convert sketches into technical drawings P1 Performance CD13- 02 Communicate design ideas with two-dimensional (2-D) computer aided design software P1 Performance PD07 Establish project design goals P1 Performance DD04 Source/research suppliers P2 Knowledge DD06- 02 Construction materials P2 Knowledge DD07- 03 Lighting design P2 Knowledge DD07- 04 Acoustic design P2 Knowledge 5. Any Events / Conferences you participated 6. Your Plan for Next Month. Appendices • Training Plan • Monthly Attendance Sheet • NOS report
Month: M3 / 15 Apr Date Day Time In Time Out Total Hours Apprentice Signature 34 17/4/2026 Friday 35 18/4/2026 Saturday 36 19/4/2026 Sunday 37 20/4/2026 Monday 1:00 PM 5:30 PM 4.5 hrs 38 21/4/2026 Tuesday 9:30 AM 5:30 PM 8 hrs 39 22/4/2026 Wednesday 40 23/4/2026 Thursday 41 24/4/2026 Friday 42 25/4/2026 Saturday 43 26/4/2026 Sunday 44 27/4/2026 Monday 1:00 PM 5:30 PM 4.5 hrs 45 28/4/2026 Tuesday 9:30 AM 5:30 PM 8 hrs 46 29/4/2026 Wednesday 9:30 AM 5:30 PM 8 hrs 47 30/4/2026 Thursday 12:00 PM 5:30 PM 5.5 hrs 48 1/5/2026 Friday 49 2/5/2026 Saturday 50 3/5/2026 Sunday 8:30 AM 5:00 PM 8.5 hrs 51 4/5/2026 Monday 1:00 PM 5:30 PM 4.5 hrs 52 5/5/2026 Tuesday 9:30 AM 5:30 PM 8 hrs 53 6/5/2026 Wednesday 9:30 AM 6:30 PM 10 hrs 54 7/5/2026 Thursday 1:00 PM 5:30 PM 4.5 hrs 55 8/5/2026 Friday 56 9/5/2026 Saturday 57 10/5/2026 Sunday 8:30 AM 5:00 PM 8.5 hrs 58 11/5/2026 Monday 1:00 PM 5:30 PM 4.5 hrs 59 12/5/2026 Tuesday 9:30 AM 5:30 PM 8 hrs 60 13/5/2026 Wednesday 8:30 AM 5:00 PM 8.5 hrs 61 14/5/2026 Thursday 1:00 PM 5:30 PM 4.5 hrs 62 15/5/2026 Friday 63 16/5/2026 Saturday 64 17/5/2026 Sunday 8:30 AM 5:00 PM 8.5 hrs Workplace mentor Signature: Attendance Total 28 Workplace Name: AJi group Workplace mentor: Eng . Hamza Bustanji Daily Apprenticeship Attendance Sheet Apprentice Name: Farah Abuzaid 9:30 AM 5:30 PM 8 hrs9:30 AM 5:30 PM 8 hrs
OIP-02-02, Rev.1.0 NOS Report Form NOS REPORT MONTH 3 STUDENT NAME: FARAH ABUZAID COMPANY: AJI GROUP Chapter Name of NOS: Number of NOS: 1 Programming & Analysis (Pre Design Phase) 1/15 2 Project Planning & Conceptual Design 7/17 3 Design Development, Detailed Design and Construction Informtion 5/29 4 Project Management 0 5 Supervision 0 6 Construction Management 0 **Performance criteria of the NOS and how you applied it in your company ** Include all the Competencies (Code/The Competency/How you applied it) (Explain and include evidence from your work)
OIP-02-02, Rev.1.0 NOS Report Form Chapter 1 PROGRAMMING & ANALYSIS (PRE DESIGN PHASE) 1.1 RELATED PROJECTS : I will use the Project No. listed in the table below as a reference for each competency. For more details on how each competency was achieved, please refer to the corresponding monthly reports submitted with this NOS report. Project name Project No. Aleyon Oasis P1 VOCO Hotel P2 1.2 COMPETENCY ACHIEVEMENT Competencies Details Coverage Status Category Related project NO. How the Competency Was Achieved No. Competency PD01 Determine the impact of applicable zoning and development ordinances to identify project constraints. ✗ Performance Knowledge ____ ___________________________________ PD02 Perform site analysis, including context, climate, approach and access, environment, views, solar access, noise, and other relevant factors. ✗ Performance Knowledge ____ ___________________________________ PD02- 01 Prepare site analysis diagrams to document existing conditions, site features, infrastructure, and regulatory requirements. ✗ Performance Knowledge ____ ___________________________________ PD02- 02 Evaluate the opportunities and constraints of alternative sites. ✗ Performance Knowledge ____ ___________________________________ PD02- 03 Determine the impact of environmental, zoning, and other regulations on the site. ✗ Performance Knowledge ____ ___________________________________ PD03 Evaluate the results of feasibility studies to determine the project’s financial viability. ✗ Performance Knowledge ____ ___________________________________ PD04 Establish sustainability goals affecting building performance. ✗ Performance Knowledge ____ ___________________________________ PD05 Apply a checklist of potential strategies with reference to green building rating systems. ✗ Performance Knowledge ____ ___________________________________
OIP-02-02, Rev.1.0 NOS Report Form PD06 Prepare diagrams illustrating spatial relationships and functional adjacencies. ✗ Performance Knowledge ____ ___________________________________ PD07 Establish project design goals. ✓ Performance Knowledge P1 P1 – Aleyon Oasis: Developed the villa concept and design approach based on the project objectives and site conditions. PD08 Consider recommendations from geotechnical studies when establishing design parameters. ✗ Performance Knowledge ____ ___________________________________ PD09 Assist the client in preparing the building program, including the list of spaces and their characteristics. ✗ Performance Knowledge ____ ___________________________________ PD10 Gather information about the client’s vision, goals, budget, and schedule to validate the project scope and program. ✗ Performance Knowledge ____ ___________________________________ PD11 Assess the environmental impact to formulate design decisions. ✗ Performance Knowledge ____ ___________________________________ PD12 Review legal documents related to the site to determine project constraints. ✗ Performance Knowledge ____ ___________________________________ Completed : 6.7% 1+14=15 0 0 Chapter 2 PROJECT PLANNING & CONCEPTUAL DESIGN 2.1 RELATED PROJECTS : I will use the Project No. listed in the table below as a reference for each competency. For more details on how each competency was achieved, please refer to the corresponding monthly reports submitted with this NOS report. Project name Project No. Aleyon Oasis P1 VOCO Hotel P2
OIP-02-02, Rev.1.0 NOS Report Form 2.2 COMPETENCY ACHIEVEMENT Level of achievement of the required Programming and Analysis competencies during the internship period. Competencies Details Covera ge Status Category Related project NO. How the Competency Was Achieved No. Competency CD01 Perform building code analysis. ✗ Performance Knowledge ____ ___________________________________ CD02 Define requirements for site survey based on the established project scope. ✗ Performance Knowledge ____ ___________________________________ CD03 Select materials, finishes, and systems based on technical properties and aesthetic requirements. ✓ Performance Knowledge P2 P2 – VOCO Hotel: Studied the acoustic performance of different building elements and materials, including wall constructions, concrete floors, gypsum ceilings, and laminated glazing, and how their properties affect sound insulation. CD04 Determine human comfort levels and corresponding design parameters for building engineering systems. ✓ Performance Knowledge P2 P2 – VOCO Hotel: Studied the acoustic comfort requirements for hotel spaces, including background noise limits, sound insulation targets, floor impact noise, and reverberation time requirements. CD05 Prepare conceptual design alternatives for client review. ✓ Performance Knowledge P1 P1 – Aleyon Oasis: Prepared and compared two site layout and planning options (Option 1 and Option 2) to evaluate the conceptual alternatives. CD06 Perform massing and volumetric studies. ✓ Performance Knowledge P1 P1 – Aleyon Oasis: Created site massing sketches and developed a conceptual massing model for project presentations. CD07 Prepare Cost of Work estimates. ✗ Performance Knowledge ____ ___________________________________ CD08 Apply principles of historic preservation for projects involving building restoration or renovation. ✗ Performance Knowledge ____ ___________________________________ CD09 Apply understanding of evolving sustainable design strategies and technologies, as well as green building rating systems. ✗ Performance Knowledge ____ ___________________________________ CD10 Design landscape elements for the site. ✗ Performance Knowledge ____ ___________________________________ CD11 Convert sketches into technical drawings. ✓ Performance Knowledge P1 P1 – Aleyon Oasis: Converted conceptual sketches and planning ideas into organized architectural drawings for the project. CD12 Present conceptual design ideas orally. ✗ Performance Knowledge ____ ___________________________________ CD13 Communicate design ideas graphically. ✗ Performance Knowledge ____ ___________________________________ CD13- 01 Communicate design ideas using hand drawings. ✗ Performance Knowledge ____ ___________________________________ CD13- 02 Communicate design ideas using two-dimensional (2D) computer- aided design software. ✓ Performance Knowledge P1 P1 – Aleyon Oasis: Prepared the architectural site plan layout and design drawings using AutoCAD. CD13- 03 Communicate design ideas using three-dimensional (3D) computer- aided design software. ✓ Performance Knowledge P1 P1 – Aleyon Oasis: Developed a 3D model of the villa type to communicate the proposed architectural design. CD13- 04 Communicate design ideas using BIM software. ✗ Performance Knowledge ____ ___________________________________ Completed : 41.2% 7+10=17 4 2
OIP-02-02, Rev.1.0 NOS Report Form Chapter 3 DESIGN DEVELOPMENT, DETAILED DESIGN AND CONSTRUCTION INFORMATION 3.1 RELATED PROJECTS : I will use the Project No. listed in the table below as a reference for each competency. For more details on how each competency was achieved, please refer to the corresponding monthly reports submitted with this NOS report. Project name Project No. Aleyon Oasis P1 VOCO Hotel P2 3.2 COMPETENCY ACHIEVEMENT Level of achievement of the required Programming and Analysis competencies during the internship period. Competencies Details Coverage Status Category Related project NO. How the Competency Was Achieved No. Competency DD01 Coordinate design work of consultants. ✗ Performance Knowledge ____ ___________________________________ DD02 Coordinate design work of in- house team members. ✗ Performance Knowledge ____ ___________________________________ DD03 Prepare submittals for regulatory approval. ✗ Performance Knowledge ____ ___________________________________ DD04 Source and research suppliers. ✓ Performance Knowledge P2 P2 – VOCO Hotel: Attended a technical workshop with USG and Estithiya suppliers to learn about ceiling products, installation methods, spans, and manufacturer recommendations. DD05 Select furniture, fixtures, and equipment that meet the client’s design requirements and needs. ✗ Performance Knowledge ____ ___________________________________ DD06 Apply knowledge in construction technology. ✗ Performance Knowledge ____ ___________________________________ DD06- 01 Apply knowledge of construction systems. ✗ Performance Knowledge ____ ___________________________________
OIP-02-02, Rev.1.0 NOS Report Form DD06- 02 Apply knowledge of construction materials. ✓ Performance Knowledge P2 P2 – VOCO Hotel: Learned how construction materials and assemblies contribute to acoustic performance, including hollow block walls, concrete slabs, gypsum board ceilings, laminated glazing, and acoustic insulation. DD06- 03 Apply knowledge of construction processes. ✗ Performance Knowledge ____ ___________________________________ DD07 Develop and integrate building systems design solutions. ✗ Performance Knowledge P2 P2 – VOCO Hotel: Studied how HVAC and mechanical systems are coordinated with acoustic requirements through vibration isolation, acoustic duct insulation, silencers, flexible connections, and noise-control measures. DD07- 01 Develop and integrate heating, ventilation, and air- conditioning systems. ✗ Performance Knowledge ____ ___________________________________ DD07- 02 Develop and integrate plumbing and sanitary systems. ✗ Performance Knowledge ____ ___________________________________ DD07- 03 Develop and integrate lighting design. ✓ Performance Knowledge P2 P2 – VOCO Hotel: Learned how lighting layouts are coordinated with acoustic ceiling systems and HVAC services for functional and acoustic performance. DD07- 04 Develop and integrate acoustic design. ✓ Performance Knowledge P2 P2 – VOCO Hotel: Reviewed the acoustic assessment covering environmental noise, sound insulation, reverberation, acoustic treatment, and recommendations for improving acoustic comfort in guest rooms and public spaces. DD08 Advance green building elements. ✗ Performance Knowledge ____ ___________________________________ DD08- 01 Develop low-impact social, environmental, and economic design solutions. ✗ Performance Knowledge ____ ___________________________________ DD08- 02 Apply knowledge of materials and technologies specific to sustainable design. ✗ Performance Knowledge ____ ___________________________________ DD08- 03 Apply principles of climate- responsive design. ✗ Performance Knowledge ____ ___________________________________ DD08- 04 Enhance energy efficiency. ✗ Performance Knowledge ____ ___________________________________ DD08- 05 Apply certification systems. ✗ Performance Knowledge ____ ___________________________________ DD09 Put together construction information packages. ✗ Performance Knowledge ____ ___________________________________ DD09- 01 Develop construction drawings, including plans, sections, elevations, wall sections, details, and schedules. ✗ Performance Knowledge ____ ___________________________________ DD09- 02 Survey quantities to prepare Bills of Quantities. ✗ Performance Knowledge ____ ___________________________________ DD09- 03 Develop project specifications. ✗ Performance Knowledge ____ ___________________________________ DD10 Review and comply with building codes, including fire safety and accessibility requirements. ✗ Performance Knowledge ____ ___________________________________
OIP-02-02, Rev.1.0 NOS Report Form DD11 Contribute to Building Information Modelling. ✗ Performance Knowledge ____ ___________________________________ DD11- 01 Build digital models using BIM modelling software. ✗ Performance Knowledge ____ ___________________________________ DD11- 02 Develop or reinforce the transition to BIM. ✗ Performance Knowledge ____ ___________________________________ DD11- 03 Manage BIM operations. ✗ Performance Knowledge ____ ___________________________________ Completed : 17.2% 5+24=29 2 3 Chapter 4 Chapter 5 Chapter 6
OIP-02-03, Rev.1.0 Final Report 4TH MONTH REPORT 15/5/2026-15/6/2026
Email 22110059@htu.edu.jo Phone 0799864046 Address Amman Apprenticeship ReportSchool of Built Environment Engineering Apprenticeship Monthly Report Student Name: Farah Abuzaid Student ID: 22110059 Major: Architectural Engineering Apprenticeship Mentor:Arch. Jomana Alawi Company Name: AJi group Industry Mentor: Eng . Hamza Bustanji Date of Report:5/15/2026 Report Type: Fourth Monthly Report Dates: 5/15/2025 – 6/16/2025
Table of Contents I. Apprenticeship Monthly Report ........................................................................1 II. General Introduction ..........................................................................................1 III. Section 1: Office Work (Design Phases) ............................................................1 Project 1 ......................................................................................................................................... 1 Task 1 : change links in rivet for the hotel rooms ...................................................................... 1 Task 2 :change the rooms name according to the new room matrix excel file ...................... 2 Task 3 :sheets new room legend ................................................................................................. 3 Task 4 :the output in pdf format .................................................. Error! Bookmark not defined. List of Achieved Competencies: ................................................................................................... 7 Project 2 ......................................................................................................................................... 8 Task 1 : Imported and developed the office plans from PDF drawings into a Revit model, including the surrounding streets, site levels, and road slopes. .............................................. 8 Task 2 : façade design studies and elevation ........................................................................... 11 List of Achieved Competencies: ................................................................................................. 12 IV. Section 2 : Site Supervision ............................................................................. 14 V. Section 3 : Project Management...................................................................... 14 VI. Section 4: Executive Summary ........................................................................ 14 VII. Appendices........................................................................................................ 15 Training Plan ................................................................................................................................ 15 Monthly Attendance Sheet ......................................................................................................... 15 NOS report ................................................................................................................................... 15
Farah’s Monthly Report PG. 1OIP-02-01, Rev.1.0 General Introduction Section 1: Office Work (Design Phases) Project 1 Project Name: VOCO Hotel Project Location: Aqaba , Jordan Project Phase: Construction Documentation Description of Project: Task 1 : change links in rivet for the hotel rooms Detailed Program
Farah’s Monthly Report PG. 2OIP-02-01, Rev.1.0 Task 2 :change the rooms name according to the new room matrix excel file Task 3 :sheets new room legend Task 4 :the output in pdf format Before After
Farah’s Monthly Report PG. 3OIP-02-01, Rev.1.0 Task 3 :sheets new room legend Notes :
Farah’s Monthly Report PG. 4OIP-02-01, Rev.1.0
Farah’s Monthly Report PG. 5OIP-02-01, Rev.1.0
Farah’s Monthly Report PG. 6OIP-02-01, Rev.1.0
Farah’s Monthly Report PG. 7OIP-02-01, Rev.1.0 → The location of the shear column was shifted by 20 cm to accommodate the relocated door in the linked model. We adjusted the structural link accordingly and then reloaded the structural link to update the changes. List of Achieved Competencies: Code Competency Description How? Type DD11 Contribute to Building Information Modelling (BIM) Contributed to the Revit model by updating links, coordinating room data, and maintaining the BIM model throughout the documentation process. Performance DD11- 01 Build digital models using BIM modelling software Updated room names, coordinated room data, and modified model information within the Revit model. Performance DD09 Put together construction information packages Prepared room legends, organized documentation sheets, and assembled the drawing package for project submission. Performance
Farah’s Monthly Report PG. 8OIP-02-01, Rev.1.0 DD09- 01 Develop construction drawings (plans, sections, elevations, wall sections, details, schedules) Updated architectural documentation sheets, coordinated room schedules, and prepared the final PDF drawing set. Performance CD13- 04 Communicate design ideas with BIM software Used Revit to communicate updated architectural information through coordinated BIM documentation and layouts. Performance Project 2 Project Name:ء IDECO Project Location: Irbid/Jordan. Project Phase: Construction Documentation Description of Project: Task 1 : Imported and developed the office plans from PDF drawings into a Revit model, including the surrounding streets, site levels, and road slopes.
Farah’s Monthly Report PG. 9OIP-02-01, Rev.1.0
Farah’s Monthly Report PG. 10OIP-02-01, Rev.1.0
Farah’s Monthly Report PG. 11OIP-02-01, Rev.1.0 Task 2 : façade design studies and elevation The submitted presentation includes the Revit modeling process, elevation design, façade material selection, suggested column layout, and 3D visualizations.
Farah’s Monthly Report PG. 12OIP-02-01, Rev.1.0 List of Achieved Competencies: Code Competency Description How? Type PD02- 01 Prepare site analysis diagrams Developed the site context by modeling the surrounding streets, site levels, and road slopes in Revit to accurately represent the existing conditions. Performance CD13- 04 Communicate design ideas with BIM software Used Revit to communicate the architectural design through a coordinated BIM model. Performance DD11- 01 Build digital models using BIM modelling software Imported PDF drawings and developed a complete BIM model, including the building, surrounding roads, and topographic levels. Performance DD09- 01 Develop construction drawings (plans, sections, elevations, wall sections, details, schedules) Produced and refined architectural plans and façade elevations as part of the construction documentation process. Performance DD07 Develop and integrate building systems design solutions Developed façade studies and coordinated the building envelope with the architectural model during the design development stage. Performance
Farah’s Monthly Report PG. 13OIP-02-01, Rev.1.0 Project 3 Project Name: Aleyon Oasis , واحةالعيون Project Location: KSA Project Phase: Conceptual Design Description of Project: Task 1 : master plan Option 1 : Option 1 : Option 2 :
Farah’s Monthly Report PG. 14OIP-02-01, Rev.1.0 List of Achieved Competencies: Code Competency Description Type PD02-02 Evaluate opportunities and constraints of alternative sites Performance PD08 Consider recommendations from geotechnical studies when establishing design parameters Performance PD09 Assist client in preparing building program including list of spaces and their characteristics Performance Section 2 : Site Supervision Section 3 : Project Management Section 4: Executive Summary 1. Any problems / Challenges and how did you overcome them? 2. Any training courses you attended during the apprenticeship, whether you opted for independently or through the employer. • Name of the course • Main Topics • Certificate (Include merged file in appendices or attach a copy) 3. Technical and non-technical skills • Technical • Non-Technical 4. Did you work on the competencies: ▪ Over-All Achieved Competencies: Code Competency Name Project No. Type DD11 Contribute to Building Information Modelling (BIM) P1 Performance
Farah’s Monthly Report PG. 15OIP-02-01, Rev.1.0 DD11- 01 Build digital models using BIM modelling software P1, P2 Performance DD09 Put together construction information packages P1 Performance DD09- 01 Develop construction drawings (plans, sections, elevations, wall sections, details, schedules) P1, P2 Performance CD13- 04 Communicate design ideas with BIM software P1, P2 Performance PD02- 01 Prepare site analysis diagrams P2 Performance DD07 Develop and integrate building systems design solutions P2 Performance 5. Any Events / Conferences you participated 6. Your Plan for Next Month. Appendices • Training Plan • Monthly Attendance Sheet • NOS report Code Competency Name M1 M2 M3 M4 Type PD01 Determine impact of applicable zoning and development ordinances to determine project constraints ✓ Performance CompetencyTracking Matrix
Farah’s Monthly Report PG. 16OIP-02-01, Rev.1.0 PD02 Perform Site analysis (Context, climate, approach and access, environment, views, solar access, noise, etc.) ✓ ✓ Performance PD02- 01 Prepare site analysis diagrams to document existing conditions, features, infrastructure, and regulatory requirements ✓ ✓ ✓ Performance PD06 Prepare diagrams illustrating spatial relationships and functional adjacencies ✓ Performance PD07 Establish project design goals ✓ ✓ Performance PD10 Gather information about client’s vision, goals, budget, and schedule to validate project scope and program ✓ Performance CD01 Perform building code analysis ✓ Performance CD03 Select materials, finishes, and systems based on technical properties and aesthetic requirements ✓ ✓ Performance CD04 Determine human comfort levels and corresponding design parameters for building engineering systems ✓ Performance CD05 Prepare conceptual design alternatives for client review ✓ ✓ Performance CD06 Perform massing and volumetric studies ✓ Performance CD11 Convert sketches into technical drawings ✓ ✓ Performance CD12 Present conceptual design ideas orally ✓ Performance CD13 Communicate design ideas graphically ✓ Performance CD13- 02 Communicate design ideas with two- dimensional (2-D) computer aided design software ✓ ✓ ✓ Performance
Farah’s Monthly Report PG. 17OIP-02-01, Rev.1.0 CD13- 03 Communicate design ideas with three- dimensional (3-D) computer aided design software ✓ ✓ Performance CD13- 04 Communicate design ideas with BIM software ✓ ✓ ✓ Performance DD01 Coordinate design work of consultants ✓ Performance DD04 Source/research suppliers ✓ Knowledge DD05 Select furniture, fixtures, and equipment that meet client’s design requirements and needs ✓ Performance DD06- 02 Construction materials ✓ ✓ Knowledge DD07 Develop and integrate building systems design solutions ✓ ✓ Performance DD07- 03 Lighting design ✓ ✓ Performance DD07- 04 Acoustic design ✓ Knowledge DD09 Put together construction information packages ✓ ✓ Performance DD09- 01 Develop construction drawings (plans, sections, elevations, wall sections, details, schedules) ✓ ✓ ✓ Performance DD11 Contribute to Building Information Modelling (BIM) ✓ Performance DD11- 01 Build digital models using BIM modelling software ✓ ✓ Performance PM01 Participate in pre-construction, pre- installation, and regular progress meetings with design team ✓ Performance
Farah’s Monthly Report PG. 18OIP-02-01, Rev.1.0 PM03 Collaborate with stakeholders during design process to maintain design intent and comply with owner specifications ✓ Performance PM07 Prepare written communications related to design ideas, project documentation, and contracts ✓ Performance S01 Review shop drawings and submittals during construction for conformance with design intent ✓ Performance S03 Complete field reports to document field observations from construction site visits ✓ Performance PD02- 02 Evaluate opportunities and constraints of alternative sites ✓ Performance PD08 Consider recommendations from geotechnical studies when establishing design parameters ✓ Performance PD09 Assist client in preparing building program including list of spaces and their characteristics ✓ Performance
Month: M4 / 15 May Date Day Time In Time Out Total Hours Apprentice Signature 34 18/5/2026 Monday 1:00 PM 5:30 PM 4.5 hrs 35 19/5/2026 Tuesday 36 20/5/2026 Wednesday 37 21/5/2026 Thursday 1:00 PM 5:30 PM 4.5 hrs 38 22/5/2026 Friday 39 23/5/2026 Saturday 40 24/5/2026 Sunday 8:30 AM 5:00 PM 8.5 hrs 41 25/5/2026 Monday 42 25/5/2026 Tuesday 43 26/5/2026 Wednesday 44 27/5/2026 Thursday 45 28/5/2026 Friday 46 29/5/2026 Saturday 47 30/5/2026 Sunday 48 31/5/2026 Monday 1:00 PM 5:30 PM 4.5 hrs 49 1/6/2026 Tuesday 8:30 AM 5:00 PM 8.5 hrs 50 2/6/2026 Wednesday 8:30 AM 5:00 PM 8.5 hrs 51 3/6/2026 Thursday 1:00 PM 5:30 PM 4.5 hrs 52 4/6/2026 Friday 53 5/6/2026 Saturday 54 6/6/2026 Sunday 1:00 PM 5:30 PM 4.5 hrs 55 7/6/2026 Monday 1:00 PM 5:30 PM 4.5 hrs 56 8/6/2026 Tuesday 57 9/6/2026 Wednesday 58 10/6/2026 Thursday 8:30 AM 5:00 PM 8.5 hrs 59 11/6/2026 Friday 60 12/6/2026 Saturday 61 13/6/2026 Sunday 8:30 AM 5:00 PM 8.5 hrs 62 14/6/2026 Monday 1:00 PM 5:30 PM 4.5 hrs 63 15/6/2026 Tuesday 8:30 AM 5:00 PM 8.5 hrs 64 16/6/2026 Wednesday 8:30 AM 5:00 PM 8.5 hrs Workplace mentor Signature: Attendance Total 17 Apprentice Name: Farah Abuzaid Workplace Name: AJi group Workplace mentor: Eng . Hamza Bustanji Daily Apprenticeship Attendance Sheet
OIP-02-02, Rev.1.0 NOS Report Form NOS REPORT MONTH 4 STUDENT NAME: FARAH ABUZAID COMPANY: AJI GROUP Chapter Name of NOS: Number of NOS: 1 Programming & Analysis (Pre Design Phase) 5 2 Project Planning & Conceptual Design 1 3 Design Development, Detailed Design and Construction Informtion 4 4 Project Management 0 5 Supervision 0 6 Construction Management 0 **Performance criteria of the NOS and how you applied it in your company ** Include all the Competencies (Code/The Competency/How you applied it) (Explain and include evidence from your work)
OIP-02-02, Rev.1.0 NOS Report Form Chapter 1 PROGRAMMING & ANALYSIS (PRE DESIGN PHASE) 1.1 RELATED PROJECTS : I will use the Project No. listed in the table below as a reference for each competency. For more details on how each competency was achieved, please refer to the corresponding monthly reports submitted with this NOS report. Project name Project No. VOCO P1 IDECO P2 Aleyon Oasis P3 1.2 COMPETENCY ACHIEVEMENT Competencies Details Coverage Status Category Related project NO. How the Competency Was Achieved No. Competency PD01 Determine the impact of applicable zoning and development ordinances to identify project constraints. ✗ Performance Knowledge ____ ______________________ PD02 Perform site analysis, including context, climate, approach and access, environment, views, solar access, noise, and other relevant factors. ✗ Performance Knowledge ____ ______________________ PD02- 01 Prepare site analysis diagrams to document existing conditions, site features, infrastructure, and regulatory requirements. ✓ Performance Knowledge P2 Developed the site context in Revit by modeling the surrounding streets, site levels, and road slopes to accurately represent the existing site conditions. PD02- 02 Evaluate the opportunities and constraints of alternative sites. ✓ Performance Knowledge P3 Listed as an achieved competency through the master plan study and evaluation of alternative site options. PD02- 03 Determine the impact of environmental, zoning, and other regulations on the site. ✓ Performance Knowledge P3 Evaluated the site constraints and applicable environmental and zoning considerations during the master plan and conceptual design process. PD03 Evaluate the results of feasibility studies to determine the project’s financial viability. ✗ Performance Knowledge ____ ______________________ PD04 Establish sustainability goals affecting building performance. ✗ Performance Knowledge ____ ______________________ PD05 Apply a checklist of potential strategies with reference to green building rating systems. ✗ Performance Knowledge ____ ______________________
OIP-02-02, Rev.1.0 NOS Report Form PD06 Prepare diagrams illustrating spatial relationships and functional adjacencies. ✗ Performance Knowledge ____ ______________________ PD07 Establish project design goals. ✗ Performance Knowledge ____ ______________________ PD08 Consider recommendations from geotechnical studies when establishing design parameters. ✓ Performance Knowledge P3 Listed as an achieved competency within the conceptual design/master plan study. PD09 Assist the client in preparing the building program, including the list of spaces and their characteristics. ✓ Performance Knowledge P3 Listed as an achieved competency within the conceptual design/master plan study. PD10 Gather information about the client’s vision, goals, budget, and schedule to validate the project scope and program. ✗ Performance Knowledge ____ ______________________ PD11 Assess the environmental impact to formulate design decisions. ✗ Performance Knowledge ____ ______________________ PD12 Review legal documents related to the site to determine project constraints. ✗ Performance Knowledge ____ ______________________ Completed : 33% 5+01=51 4 0 Chapter 2 PROJECT PLANNING & CONCEPTUAL DESIGN 2.1 RELATED PROJECTS : I will use the Project No. listed in the table below as a reference for each competency. For more details on how each competency was achieved, please refer to the corresponding monthly reports submitted with this NOS report. Project name Project No. VOCO P1 IDECO P2 Aleyon Oasis P3
OIP-02-02, Rev.1.0 NOS Report Form 2.2 COMPETENCY ACHIEVEMENT Level of achievement of the required Programming and Analysis competencies during the internship period. Competencies Details Cover age Status Category Related project NO. How the Competency Was Achieved No. Competency CD01 Perform building code analysis. ✗ Performance Knowledge ____ ______________________ CD02 Define requirements for site survey based on the established project scope. ✗ Performance Knowledge ____ ______________________ CD03 Select materials, finishes, and systems based on technical properties and aesthetic requirements. ✗ ✗ Knowledge ____ ______________________ CD04 Determine human comfort levels and corresponding design parameters for building engineering systems. ✗ ✗ Knowledge ____ ______________________ CD05 Prepare conceptual design alternatives for client review. ✗ ✗ Knowledge ____ ______________________ CD06 Perform massing and volumetric studies. ✗ ✗ Knowledge ____ ______________________ CD07 Prepare Cost of Work estimates. ✗ ✗ Knowledge ____ ______________________ CD08 Apply principles of historic preservation for projects involving building restoration or renovation. ✗ ✗ Knowledge ____ ______________________ CD09 Apply understanding of evolving sustainable design strategies and technologies, as well as green building rating systems. ✗ ✗ Knowledge ____ ______________________ CD10 Design landscape elements for the site. ✗ ✗ Knowledge ____ ______________________ CD11 Convert sketches into technical drawings. ✗ ✗ Knowledge ____ ______________________ CD12 Present conceptual design ideas orally. ✗ ✗ Knowledge ____ ______________________ CD13 Communicate design ideas graphically. ✗ ✗ Knowledge ____ ______________________ CD13- 01 Communicate design ideas using hand drawings. ✗ ✗ Knowledge ____ ______________________ CD13- 02 Communicate design ideas using two-dimensional (2D) computer- aided design software. ✗ ✗ Knowledge ____ ______________________ CD13- 03 Communicate design ideas using three-dimensional (3D) computer- aided design software. ✗ ✗ Knowledge ____ ______________________ CD13- 04 Communicate design ideas using BIM software. ✓ Performance Knowledge P1.P2 Used Revit to communicate updated architectural information through coordinated BIM documentation and layouts in VOCO, and through a coordinated BIM model for IDECO. Completed : 5.9% 16+1= 17 0 0
OIP-02-02, Rev.1.0 NOS Report Form Chapter 3 DESIGN DEVELOPMENT, DETAILED DESIGN AND CONSTRUCTION INFORMATION 3.1 RELATED PROJECTS : I will use the Project No. listed in the table below as a reference for each competency. For more details on how each competency was achieved, please refer to the corresponding monthly reports submitted with this NOS report. Project name Project No. VOCO P1 IDECO P2 Aleyon Oasis P3 3.2 COMPETENCY ACHIEVEMENT Level of achievement of the required Programming and Analysis competencies during the internship period. Competencies Details Coverage Status Category Related project NO. How the Competency Was Achieved No. Competency DD01 Coordinate design work of consultants. ✗ Performance Knowledge ____ _________________________ DD02 Coordinate design work of in- house team members. ✗ Performance Knowledge ____ _________________________ DD03 Prepare submittals for regulatory approval. ✗ Performance Knowledge ____ _________________________ DD04 Source and research suppliers. ✗ Performance Knowledge ____ _________________________ DD05 Select furniture, fixtures, and equipment that meet the client’s design requirements and needs. ✗ Performance Knowledge ____ _________________________ DD06 Apply knowledge in construction technology. ✗ Performance Knowledge ____ _________________________ DD06- 01 Apply knowledge of construction systems. ✗ Performance Knowledge ____ _________________________ DD06- 02 Apply knowledge of construction materials. ✗ Performance Knowledge ____ _________________________ DD06- 03 Apply knowledge of construction processes. ✗ Performance Knowledge ____ _________________________
OIP-02-02, Rev.1.0 NOS Report Form DD07 Develop and integrate building systems design solutions. ✓ Performance Knowledge P2 Developed façade studies and coordinated the building envelope with the architectural model during the design development stage. DD07- 01 Develop and integrate heating, ventilation, and air- conditioning systems. ✗ Performance Knowledge ____ _________________________ DD07- 02 Develop and integrate plumbing and sanitary systems. ✗ Performance Knowledge ____ _________________________ DD07- 03 Develop and integrate lighting design. ✗ Performance Knowledge ____ _________________________ DD07- 04 Develop and integrate acoustic design. ✗ Performance Knowledge ____ _________________________ DD08 Advance green building elements. ✗ Performance Knowledge ____ _________________________ DD08- 01 Develop low-impact social, environmental, and economic design solutions. ✗ Performance Knowledge ____ _________________________ DD08- 02 Apply knowledge of materials and technologies specific to sustainable design. ✗ Performance Knowledge ____ _________________________ DD08- 03 Apply principles of climate- responsive design. ✗ Performance Knowledge ____ _________________________ DD08- 04 Enhance energy efficiency. ✗ Performance Knowledge ____ _________________________ DD08- 05 Apply certification systems. ✗ Performance Knowledge ____ _________________________ DD09 Put together construction information packages. ✓ Performance Knowledge P1 Prepared room legends, organized documentation sheets, and assembled the drawing package for project submission. DD09- 01 Develop construction drawings, including plans, sections, elevations, wall sections, details, and schedules. ✓ Performance Knowledge P1, P2 Updated architectural documentation sheets, coordinated room schedules, and prepared the final PDF drawing set. Produced and refined architectural plans and façade elevations as part of the construction documentation process. DD09- 02 Survey quantities to prepare Bills of Quantities. ✗ Performance Knowledge ____ _________________________ DD09- 03 Develop project specifications. ✗ Performance Knowledge ____ _________________________ DD10 Review and comply with building codes, including fire safety and accessibility requirements. ✗ Performance Knowledge ____ _________________________ DD11 Contribute to Building Information Modelling. ✗ Performance Knowledge P1 Updated Revit links, coordinated room data, and maintained the BIM model throughout the documentation process. DD11- 01 Build digital models using BIM modelling software. ✓ Performance Knowledge P1. P2 Updated room names, coordinated room data, and modified model information within the Revit model. Imported PDF drawings and developed a complete BIM model including the building, surrounding roads, and topographic levels. DD11- 02 Develop or reinforce the transition to BIM. ✗ Performance Knowledge ____ _________________________
OIP-02-02, Rev.1.0 NOS Report Form DD11- 03 Manage BIM operations. ✗ Performance Knowledge ____ _________________________ Completed : 13.8% 4+25=29 0 0 Chapter 4 Chapter 5 Chapter 6
OIP-02-03, Rev.1.0 Final Report 5TH MONTH REPORT 15/6/2026-15/7/2026
Email 22110059@htu.edu.jo Phone 0799864046 Address Amman Apprenticeship ReportSchool of Built Environment Engineering Apprenticeship Monthly Report Student Name: Farah Abuzaid Student ID: 22110059 Major: Architectural Engineering Apprenticeship Mentor:Arch. Jomana Alawi Company Name: AJi group Industry Mentor: Eng . Hamza Bustanji Date of Report:5/15/2026 Report Type: Fifth Monthly Report Dates: 5/15/2025 – 7/15/2025
Table of Contents I. Apprenticeship Monthly Report ........................................................................1 II. General Introduction ..........................................................................................1 III. Section 1: Office Work (Design Phases) ............................................................1 Project 1 ......................................................................................................................................... 1 Task 1 : change links in rivet for the hotel rooms ...................................................................... 1 Task 2 :change the rooms name according to the new room matrix excel file ...................... 1 Task 3 :sheets new room legend ................................................. Error! Bookmark not defined. Task 4 :the output in pdf format .................................................. Error! Bookmark not defined. List of Achieved Competencies: ................................................................................................... 1 Project 2 ......................................................................................................................................... 1 Task 1 : Imported and developed the office plans from PDF drawings into a Revit model, including the surrounding streets, site levels, and road slopes. .............................................. 1 Task 2 : façade design studies and elevation ............................................................................. 1 List of Achieved Competencies: ................................................................................................... 1 IV. Section 2 : Site Supervision ...............................................................................1 V. Section 3 : Project Management........................................................................9 VI. Section 4: Executive Summary ........................................................................ 14 VII. Appendices........................................................................................................ 14 Training Plan ................................................................................................................................ 14 Monthly Attendance Sheet ......................................................................................................... 14 NOS report ................................................................................................................................... 14
Farah’s Monthly Report PG. 1OIP-02-01, Rev.1.0 General Introduction Section 1: Office Work (Design Phases) Section 2 : Site Supervision Project 1 Project Name: RACJ Project Location: AMMAN, JORDAN Project Phase: Construction Documentation Description of Project: Task 1 : DAY ONE Detailed Program
Farah’s Monthly Report PG. 2OIP-02-01, Rev.1.0 Task 2 : day two
Farah’s Monthly Report PG. 3OIP-02-01, Rev.1.0
Farah’s Monthly Report PG. 4OIP-02-01, Rev.1.0 List of Achieved Competencies: P1 Code Competency Description S07 Inspection and Approval of Construction Works S04 Review results from field reports, third-party inspections, and other test results for conformance with contract documents S07 22 Flooring S03 Complete field reports to document field observations from construction site visits S07 16 Plastering S07 18 Electrical conduits in walls and floors S07 25 Painting Project 2 Project Name: Holidayinn resort Project Location: deadsee , JORDAN Project Phase: Construction Documentation Description of Project:
Farah’s Monthly Report PG. 5OIP-02-01, Rev.1.0 Task 1 : List of Achieved Competencies:P2 Code Competency Description S07-20 Moisture insulation in roofs, floors and walls S07-21 Sanitary and Mechanical works S07-22 Flooring S07-25 Painting S02 Respond to Contractor Requests for Information
Farah’s Monthly Report PG. 6OIP-02-01, Rev.1.0 Project 3 Project Name: JEPCO Project Location: Ghamadan , JORDAN Project Phase: Construction Documentation Description of Project: Task 1 :
Farah’s Monthly Report PG. 7OIP-02-01, Rev.1.0 List of Achieved Competencies:P3 Code Competency Description S07-14 Stone works S07-23 Wood works S07-09 Scaffolding works for slabs
Farah’s Monthly Report PG. 8OIP-02-01, Rev.1.0 Project 4 Project Name: Al Rawda Secondary School for Girls – (Maintenance and Rehabilitation Works) Project Location: Al Rawda Area, Naour, Jordan, JORDAN Project Phase: Construction Documentation Description of Project: Task 1 : Cleaning the Old Bitumen and Constructing Level Pads (Wada'at) Removing the deteriorated bitumen layer and installing concrete level pads to determine the required roof slopes before screed casting.
Farah’s Monthly Report PG. 9OIP-02-01, Rev.1.0 Task 2: Roof Slope Screed Casting: Casting a cement screed layer with proper slopes towards the drainage points to prepare the roof for waterproofing works.
Farah’s Monthly Report PG. 10OIP-02-01, Rev.1.0 Task 3: Internal Wall Painting Works Repairing damaged wall surfaces, applying fillers where required, and repainting classrooms and corridors. Task 4: Floor Excavation for Plumbing Maintenance List of Achieved Competencies: P4
Farah’s Monthly Report PG. 11OIP-02-01, Rev.1.0 Code Competency Description S07 16 Plastering S07 20 Moisture insulation in roofs, floors and walls S07 21 Sanitary and Mechanical works S07 25 Sanitary and Mechanical works Project 5 Project Name: OM AL-qutain School Project Location: Jordan / Naour Project Phase: Construction Documentation Description of Project: Task 1 : Site Preparation and Excavation:
Farah’s Monthly Report PG. 12OIP-02-01, Rev.1.0 initial foundation works, beginning with the completed excavation to the required founding level. The excavation dimensions and levels were inspected, followed by reviewing the structural drawings and setting out the foundation locations. Accurate site marking ensured that all footing positions matched the approved design before foundation construction commenced. Task 2 : Foundation Base Concrete
Farah’s Monthly Report PG. 13OIP-02-01, Rev.1.0 Task 3 : Foundation Reinforcement and Formwork Task 4: Foundation Concrete Pour List of Achieved Competencies: P5 Code Competency Description S07 02 Excavation works S07 04 Scaffolding works for footings
Farah’s Monthly Report PG. 14OIP-02-01, Rev.1.0 S07 05 Footing reinforcement S07 06 Concrete works + tests Section 3 : Project Management Section 4: Executive Summary 1. Any problems / Challenges and how did you overcome them? 2. Any training courses you attended during the apprenticeship, whether you opted for independently or through the employer. • Name of the course • Main Topics • Certificate (Include merged file in appendices or attach a copy) 3. Technical and non-technical skills • Technical • Non-Technical 4. Did you work on the competencies: ▪ Over-All Achieved Competencies: 5. Any Events / Conferences you participated 6. Your Plan for Next Month. Appendices • Training Plan • Monthly Attendance Sheet • NOS report
Month: M5 15/07/2026 Date Day Time In Time Out Total Hours Apprentice Signature 1 6/15/2026 Monday 2 6/16/2026 Tuesday 3 6/17/2026 Wednesday 8:50 AM 4:30 PM 7:30 hrs 4 6/18/2026 Thursday 8:50 AM 4:30 PM 7:30 hrs 5 6/19/2026 Friday 6 6/20/2026 Saturday 7 6/21/2026 Sunday 8:50 AM 4:30 PM 7:30 hrs 8 6/22/2026 Monday 8:50 AM 4:30 PM 7:30 hrs 9 6/23/2026 Tuesday 8:50 AM 4:30 PM 7:30 hrs 10 6/24/2026 Wednesday 8:50 AM 4:30 PM 7:30 hrs 11 6/25/2026 Thursday 8:50 AM 4:30 PM 7:30 hrs 12 6/26/2026 Friday 13 6/27/2026 Saturday 14 6/28/2026 Sunday 8:50 AM 4:30 PM 7:30 hrs 15 6/29/2026 Monday 8:50 AM 4:30 PM 7:30 hrs 16 6/30/2026 Tuesday 8:50 AM 4:30 PM 7:30 hrs 18 7/1/2026 Wednesday 8:50 AM 4:30 PM 7:30 hrs 19 7/2/2026 Thursday 8:50 AM 4:30 PM 7:30 hrs 20 7/3/2026 Friday 21 7/4/2026 Saturday 22 7/5/2026 Sunday 8:50 AM 4:30 PM 7:30 hrs 23 7/6/2026 Monday 8:50 AM 4:30 PM 7:30 hrs 24 7/7/2026 Tuesday 8:50 AM 4:30 PM 7:30 hrs 25 7/8/2026 Wednesday 8:50 AM 4:30 PM 7:30 hrs 26 7/9/2026 Thursday 8:50 AM 4:30 PM 7:30 hrs 27 7/10/2026 Friday 28 7/11/2026 Saturday 29 7/12/2026 Sunday 8:50 AM 4:30 PM 7:30 hrs 30 7/13/2026 Monday 8:50 AM 4:30 PM 7:30 hrs 31 7/14/2026 Tuesday 8:50 AM 4:30 PM 7:30 hrs 32 7/15/2026 Wednesday 8:50 AM 4:30 PM 7:30 hrs Attendance Total 21 Workplace Name: Workplace mentor Signature: Daily Apprenticeship Attendance Sheet Workplace mentor: AJi group Eng . Hamza Bustanji Apprentice Name: FARAH ABUZAID
OIP-02-02, Rev.1.0 NOS Report Form NOS REPORT MONTH 5 STUDENT NAME: FARAH ABUZAID COMPANY: AJI GROUP Chapter Name of NOS: Number of NOS: 1 Programming & Analysis (Pre Design Phase) 0 2 Project Planning & Conceptual Design 0 3 Design Development, Detailed Design and Construction Informtion 0 4 Project Management 0 5 Supervision 0 6 Construction Management 0 **Performance criteria of the NOS and how you applied it in your company ** Include all the Competencies (Code/The Competency/How you applied it) (Explain and include evidence from your work)
OIP-02-02, Rev.1.0 NOS Report Form Chapter 1 Chapter 2 Chapter 3 Chapter 4 Chapter 5 SUPERVISION 5.1 RELATED PROJECTS I will use the Project No. listed in the table below as a reference for each competency. For more details on how each competency was achieved, please refer to the corresponding monthly reports submitted with this NOS report. Project name Project No. RACJ P1 Holidayinn resort P2 JEPCO P3 Al Rawda Secondary School for Girls P4 OM AL-qutain School P5 5.2 COMPETENCY ACHIEVEMENT Level of achievement of the required Programming and Analysis competencies during the internship period. Project Code Competency Name How the Competency Was Achieved P1 – RACJ S07 Inspection and Approval of Construction Works Participated in site supervision and inspection of the construction works documented during the RACJ site visits. P1 – RACJ S04 Review results from field reports, third-party inspections, and other test results for conformance with contract documents Reviewed site conditions and construction works during the site visits for conformance with the project requirements.
OIP-02-02, Rev.1.0 NOS Report Form Project Code Competency Name How the Competency Was Achieved P1 – RACJ S07- 22 Flooring Observed and inspected flooring works during the RACJ site visit. P1 – RACJ S03 Complete field reports to document field observations from construction site visits Documented observations from the RACJ construction site visits. P1 – RACJ S07- 16 Plastering Observed and inspected plastering works during the site visit. P1 – RACJ S07- 18 Electrical conduits in walls and floors Observed electrical conduit installation within walls and floors during the site visit. P1 – RACJ S07- 25 Painting Observed and inspected painting works during the site visit. P2 – Holidayinn Resort S07- 20 Moisture insulation in roofs, floors and walls Observed the moisture/waterproofing-related works within the Holiday Inn Resort project. P2 – Holidayinn Resort S07- 21 Sanitary and Mechanical works Observed sanitary and mechanical works during the site supervision visit. P2 – Holidayinn Resort S07- 22 Flooring Observed flooring works as part of the site supervision activities. P2 – Holidayinn Resort S07- 25 Painting Observed painting works during the site visit. P2 – Holidayinn Resort S02 Respond to Contractor Requests for Information Responded to contractor requests for information during the project site activities. P3 – JEPCO S07- 14 Stone works Observed and inspected stone works on the JEPCO construction site. P3 – JEPCO S07- 23 Wood works Observed and inspected wood works on the JEPCO construction site.
OIP-02-02, Rev.1.0 NOS Report Form Project Code Competency Name How the Competency Was Achieved P3 – JEPCO S07- 09 Scaffolding works for slabs Observed scaffolding works used for slab construction on the JEPCO site. P4 – Al Rawda Secondary School for Girls S07- 16 Plastering Observed plastering/repair works during the maintenance works at the school. P4 – Al Rawda Secondary School for Girls S07- 20 Moisture insulation in roofs, floors and walls Observed roof preparation works including removal of old bitumen and preparation for waterproofing. P4 – Al Rawda Secondary School for Girls S07- 21 Sanitary and Mechanical works Observed floor excavation works carried out for plumbing maintenance. P4 – Al Rawda Secondary School for Girls S07- 25 Sanitary and Mechanical works Observed the plumbing-related maintenance works during the site supervision. P5 – OM Al- Qutain School S07- 02 Excavation works Inspected excavation dimensions and levels, reviewed structural drawings, and checked the setting-out of foundation locations against the approved design. P5 – OM Al- Qutain School S07- 04 Scaffolding works for footings Observed the formwork/scaffolding associated with the footing construction before concrete works.
OIP-02-02, Rev.1.0 NOS Report Form
OIP-02-02, Rev.1.0 NOS Report Form Chapter 6
OIP-02-03, Rev.1.0 Final Report 6TH MONTH REPORT 15/7/2026-15/8/2026
Email 22110059@htu.edu.jo Phone 0799864046 Address Amman Apprenticeship ReportSchool of Built Environment Engineering Apprenticeship Monthly Report Student Name: Farah Abuzaid Student ID: 22110059 Major: Architectural Engineering Apprenticeship Mentor:Arch. Jomana Alawi Company Name: AJi group Industry Mentor: Eng . Hamza Bustanji Date of Report:5/15/2026 Report Type: Sixth Monthly Report Dates: 7/15/2025 – 8/15/2025
Table of Contents I. Apprenticeship Monthly Report ........................................................................1 II. General Introduction ..........................................................................................1 III. Section 1: Office Work (Design Phases) ............................................................1 Project 1 ......................................................................................................................................... 1 Task 1 : change links in rivet for the hotel rooms ...................................................................... 1 Task 2 :change the rooms name according to the new room matrix excel file ...................... 1 Task 3 :sheets new room legend ................................................. Error! Bookmark not defined. Task 4 :the output in pdf format .................................................. Error! Bookmark not defined. List of Achieved Competencies: ................................................................................................... 9 Project 2 ....................................................................................................................................... 10 Task 1 : Imported and developed the office plans from PDF drawings into a Revit model, including the surrounding streets, site levels, and road slopes. ............................................ 10 Task 2 : façade design studies and elevation ............................. Error! Bookmark not defined. List of Achieved Competencies: ................................................................................................. 11 IV. Section 2 : Site Supervision ............................................................................. 12 V. Section 3 : Project Management...................................................................... 38 VI. Section 4: Executive Summary ........................................................................ 38 VII. Appendices........................................................................................................ 41 Training Plan ................................................................................................................................ 41 Monthly Attendance Sheet ......................................................................................................... 41 NOS report ................................................................................................................................... 41
Farah’s Monthly Report PG. 1OIP-02-01, Rev.1.0 General Introduction Section 1: Office Work (Design Phases) Project 1 Project Name: Food Festival Project Project Location: Project Phase: Construction Documentation Description of Project: Last year, AJi Group developed the initial design for the Food Festival project. This year, Fadaa redesigned the project, while AJi Group was responsible for the documentation, site levels, and construction package. The project included several market kiosk models, with different design proposals developed by Fadaa. Task 1 : Understanding the Design and Site Zoning - Reviewed and understood the presentation package provided by Fadaa. Detailed Program
Farah’s Monthly Report PG. 2OIP-02-01, Rev.1.0 - Developed a site zoning plan identifying: • Existing buildings • Demolished buildings • New proposed buildings
Farah’s Monthly Report PG. 3OIP-02-01, Rev.1.0 - Produced two sheets: 1. Market model types . 2. Site zoning showing demolition, existing, and new buildings.
Farah’s Monthly Report PG. 4OIP-02-01, Rev.1.0 Task 2 : Site Modeling and Levels
Farah’s Monthly Report PG. 5OIP-02-01, Rev.1.0 Task 3 : Market Models • Developed the four market models in Revit.
Farah’s Monthly Report PG. 6OIP-02-01, Rev.1.0 • Prepared the three design proposals provided by Fadaa.
Farah’s Monthly Report PG. 7OIP-02-01, Rev.1.0 Task 4 : Material Selection Task 5 : Construction Package • Prepared the construction package for the four market models.
Farah’s Monthly Report PG. 8OIP-02-01, Rev.1.0
Farah’s Monthly Report PG. 9OIP-02-01, Rev.1.0 List of Achieved Competencies: Code Competency Description Why / How you achieved it PD02- 01 Prepare site analysis diagrams to document existing conditions, features, infrastructure, and regulatory requirements Developed a site zoning plan showing existing buildings, demolished buildings, and proposed new buildings, together with the site modeling and level information. Code Competency Description Why / How you achieved it CD03 Select materials, finishes, and systems based on technical properties and aesthetic requirements Prepared a material palette for the market models, including vertical strip tiles, ribbed tiles, square tiles, quartz countertop, and planter finishes. CD13- 03 Communicate design ideas with three-dimensional (3-D) computer aided design software Developed the four market models in Revit and prepared 3D representations of the different kiosk proposals. CD13- 04 Communicate design ideas with BIM software Used Revit to develop the market models and communicate the proposed kiosk designs through BIM models and drawings. Code Competency Description Why / How you achieved it DD06- 02 Construction materials Applied construction-material knowledge when developing the material palette and representing materials such as concrete, tiles, paint and other finishes in the market models. DD09 Put together construction information packages Prepared the construction package for the four market models. DD09- 01 Develop construction drawings (plans, sections, elevations, wall sections, details, schedules) Produced construction drawings for the market models, including plans/elevations and detailed drawing sheets as shown in the construction package. DD11 Contribute to Building Information Modelling (BIM) Contributed to the development of the Food Festival BIM documentation by developing the market models in Revit.
Farah’s Monthly Report PG. 10OIP-02-01, Rev.1.0 DD11- 01 Build digital models using BIM modelling software Built the four market models in Revit and developed the three design proposals provided by Fadaa. Project 2 Project Name: Holiday Inn Renovation Project Project Location: Dead Sea, Amman Project Phase: Construction Documentation Description of Project: Task 1 : The existing entrance sidewalk was too large, which limited the vehicle maneuvering area and made it difficult for buses and tourist coaches to enter and maneuver properly. Added the required hatches and material representations based on the materials provided in the project file, including insulation, brickwork, and other construction materials. The Plan Before + task The Plan After
Farah’s Monthly Report PG. 11OIP-02-01, Rev.1.0 List of Achieved Competencies: Code Competency Description Why / How you achieved it CD03 Select materials, finishes, and systems based on technical properties and aesthetic requirements Added the required material representations based on the project information, including insulation, brickwork, and other construction materials. Code Competency Description Why / How you achieved it DD06- 02 Construction materials Applied knowledge of construction materials by adding and representing insulation, brickwork and other construction materials in the drawings. DD09- 01 Develop construction drawings (plans, sections, Modified the entrance/access drawing from the before condition to the proposed after
Farah’s Monthly Report PG. 12OIP-02-01, Rev.1.0 elevations, wall sections, details, schedules) condition, including the required hatches and material representations. DD09 Put together construction information packages Worked on the project documentation by updating the drawing and incorporating the required construction/material information. Section 2 : Site Supervision Project 1 Project Name: RACJ Project Location: AMMAN, JORDAN Project Phase: Construction Documentation Description of Project: Task 1 : Phase 1–2 – Project Handover
Farah’s Monthly Report PG. 13OIP-02-01, Rev.1.0
Farah’s Monthly Report PG. 14OIP-02-01, Rev.1.0
Farah’s Monthly Report PG. 15OIP-02-01, Rev.1.0 Task 2 : Phase 3 • Project Introduction - We first met with Eng. Banan, the contractor, who reviewed the drawings submitted by AJi.
Farah’s Monthly Report PG. 16OIP-02-01, Rev.1.0 - She explained the scope of Phase 3 and the existing site conditions.
Farah’s Monthly Report PG. 17OIP-02-01, Rev.1.0 - There were some Requests for Information (RFIs) regarding certain drawings, which were raised by the contractor to AJi as the consultant. For example, the
Farah’s Monthly Report PG. 18OIP-02-01, Rev.1.0 architectural elevations do not match the structural elevations, showing a lack of coordination. - Phase 3 mainly includes structural and excavation works. • Excavation & Site Conditions - During excavation, the team found a large basalt rock underground. - The excavation had to stop.
Farah’s Monthly Report PG. 19OIP-02-01, Rev.1.0 - Bench mark - We learned that actual ground conditions can be different from the expected conditions.
Farah’s Monthly Report PG. 20OIP-02-01, Rev.1.0 - We also found main electrical lines and unknown water pipes during excavation. - The work had to stop to avoid damaging the existing utilities. • Site Coordination - The engineer explained a problem with the architectural benchmark. - The benchmark did not match the levels used in other parts of the project. Task 2 : Phase 4-5 - We learned that Phases 4 and 5 are more focused on architectural work. - The work includes demolition and architectural modifications.
Farah’s Monthly Report PG. 21OIP-02-01, Rev.1.0 List of Achieved Competencies: Code Competency Description Why / How you achieved it S07 Inspection and approval of construction works Participated in observing construction activities and understanding the inspection process during the different project phases. The report documents contractor drawing review, site conditions, excavation and coordination issues. S07- 02 Excavation works Observed the excavation works and actual site conditions, including the discovery of basalt rock underground, which caused excavation to stop. S07- 01 Surveying works: site boundaries and street alignment Gained exposure to benchmarks and site levels, including identifying a mismatch between the architectural benchmark and levels used elsewhere in the project. Project 2 Project Name: Prince Faisal Hospital Project Location: Zarqa Project Phase: Construction Documentation Description of Project:
Farah’s Monthly Report PG. 22OIP-02-01, Rev.1.0 • The project is located in Jerash and is for Prince Faisal Hospital. • The project scope includes demolition and extension works to expand the existing hospital. • The hospital serves the residents of Zarqa and Russeifa, as it is the only hospital serving the area. • The project also includes a new helicopter landing pad (helipad). • The existing helipad will be demolished and excavated to match the level of the adjacent building. • A new helipad will be constructed in a different location. Task 1 :
Farah’s Monthly Report PG. 23OIP-02-01, Rev.1.0
Farah’s Monthly Report PG. 24OIP-02-01, Rev.1.0
Farah’s Monthly Report PG. 25OIP-02-01, Rev.1.0
Farah’s Monthly Report PG. 26OIP-02-01, Rev.1.0
Farah’s Monthly Report PG. 27OIP-02-01, Rev.1.0
Farah’s Monthly Report PG. 28OIP-02-01, Rev.1.0
Farah’s Monthly Report PG. 29OIP-02-01, Rev.1.0
Farah’s Monthly Report PG. 30OIP-02-01, Rev.1.0
Farah’s Monthly Report PG. 31OIP-02-01, Rev.1.0 List of Achieved Competencies: Code Competency Description Why / How you achieved it S07 Inspection and approval of construction works Participated in site supervision and observed construction activities associated with the hospital extension, demolition and helipad works. S07- 01 Surveying works: site boundaries and street alignment Observed site setting-out/surveying activities and marked locations during the construction works. The site photos show surveying equipment and marked- out areas. S07- 02 Excavation works Observed excavation and trenching works associated with the project, including the works around the existing/new helipad and site infrastructure. S07- 05 Footing reinforcement Observed reinforcement bars and reinforcement preparation on site as part of the structural construction works. S07- 08 Reinforcement works in columns and walls Observed reinforcement assemblies and vertical reinforcement elements on the construction site. Project 3 Project Name: Jerash Health Center – Refurbishment Project Project Location: Jerash Project Phase: Construction Documentation Description of Project: • The project is located in Jerash and is an existing health center. • The project scope included a complete refurbishment, while keeping the existing structural elements. • Metal jacketing was added to strengthen the existing structural elements. • The building was originally a health center with clinics only. • The refurbishment added new services, including: • Dental clinic • Emergency department
Farah’s Monthly Report PG. 32OIP-02-01, Rev.1.0 • ENT clinic • The roof level was also extended as part of the project. • The external cladding was completely changed, including stone cladding and pergolas. • The project also included new landscaping and parking areas. • The building has glass façades as part of the new architectural design. • The project concept and design development took around 7 months, from December to July. • The construction phase took longer than the design period. Task 1 :
Farah’s Monthly Report PG. 33OIP-02-01, Rev.1.0
Farah’s Monthly Report PG. 34OIP-02-01, Rev.1.0
Farah’s Monthly Report PG. 35OIP-02-01, Rev.1.0
Farah’s Monthly Report PG. 36OIP-02-01, Rev.1.0
Farah’s Monthly Report PG. 37OIP-02-01, Rev.1.0 List of Achieved Competencies: Code Competency Description Why / How you achieved it S07 Inspection and approval of construction works Participated in reviewing/observing completed and ongoing refurbishment works, including architectural finishes and existing-building modifications. S07- 14 Stone works Observed the stone cladding works associated with the refurbished external envelope. S07- 23 Wood works Covered the architectural external works including pergolas as part of the refurbishment scope. S07- 24 Metal works The project included metal jacketing to strengthen the existing structural elements, providing exposure to metal construction works. Code Competency Description Why / How you achieved it DD09 Put together construction information packages Worked with project documentation/packages including architectural, interior, medical and signage information. DD09- 01 Develop construction drawings (plans, sections, elevations, wall sections, details, schedules) Worked with architectural plans/elevations and drawing information for the refurbished health center. DD05 Select furniture, fixtures, and equipment that meet the client’s design requirements and needs Reviewed/used equipment lists and room equipment information shown in the project documentation. DD11 Contribute to Building Information Modelling (BIM) Worked with digital project information and coordinated drawing/model information as part of the project documentation process.
Farah’s Monthly Report PG. 38OIP-02-01, Rev.1.0 Section 3 : Project Management Section 4: Executive Summary 1. Any problems / Challenges and how did you overcome them? 2. Any training courses you attended during the apprenticeship, whether you opted for independently or through the employer. • Name of the course • Main Topics • Certificate (Include merged file in appendices or attach a copy) 3. Technical and non-technical skills • Technical • Non-Technical 4. Did you work on the competencies: ▪ Over-All Achieved Competencies: Category Code Competency Name Project No. How the Competency Was Achieved PD PD02- 01 Prepare site analysis diagrams to document existing conditions, features, infrastructure, and regulatory requirements P1 – Food Festival Developed a site zoning plan identifying existing buildings, demolished buildings, and new proposed buildings, as part of understanding and documenting the site. CD CD03 Select materials, finishes, and systems based on technical properties and aesthetic requirements P1 – Food Festival + P2 – Holiday Inn For Food Festival, developed a material palette for the market models. For Holiday Inn, added the required material representations and hatches, including insulation, brickwork, and other construction materials.
Farah’s Monthly Report PG. 39OIP-02-01, Rev.1.0 CD CD13- 03 Communicate design ideas with three- dimensional (3-D) computer aided design software P1 – Food Festival Developed the market/kiosk models in Revit to represent the different design proposals in 3D. CD CD13- 04 Communicate design ideas with BIM software P1 – Food Festival + P2 – Holiday Inn Used Revit/BIM to develop and communicate the market models and to update the Holiday Inn architectural documentation and material information. DD DD05 Select furniture, fixtures, and equipment that meet client’s design requirements and needs P3 – Jerash Health Center Reviewed project documentation containing equipment information/lists as part of the refurbishment and new medical- service requirements. DD DD06- 02 Construction materials P1 – Food Festival + P2 – Holiday Inn Applied construction-material knowledge through the Food Festival material palette and by representing insulation, brickwork and other construction materials in the Holiday Inn drawings. DD DD09 Put together construction information packages P1 – Food Festival + P2 – Holiday Inn + P3 – Jerash Health Center Prepared/organized construction documentation and drawing information for the Food Festival market models, Holiday Inn entrance modification, and Jerash Health Center refurbishment documentation. DD DD09- 01 Develop construction drawings (plans, sections, elevations, wall P1 – Food Festival + P2 – Holiday Inn + P3 – Jerash Developed construction/documentation drawings for the Food Festival models; modified the Holiday Inn before/after entrance plan with material information; and worked
Farah’s Monthly Report PG. 40OIP-02-01, Rev.1.0 sections, details, schedules) Health Center with architectural plans/elevations for the Jerash Health Center refurbishment. DD DD11 Contribute to Building Information Modelling (BIM) P1 – Food Festival + P3 – Jerash Health Center Contributed to BIM-based project documentation through the development of Revit models and digital project information. DD DD11- 01 Build digital models using BIM modelling software P1 – Food Festival Built the market models in Revit, developing the different kiosk proposals into digital BIM models. S S07 Inspection and Approval of Construction Works S/P1 – RACJ + S/P2 – Prince Faisal Hospital + S/P3 – Jerash Health Center Participated in site supervision and observed/inspected construction and refurbishment activities across the three sites. S S07- 01 Surveying works: site boundaries and street alignment S/P1 – RACJ + S/P2 – Prince Faisal Hospital At RACJ, observed benchmarks and site levels and identified discrepancies between project level information. At Prince Faisal Hospital, observed site setting- out/surveying activities. S S07- 02 Excavation works S/P1 – RACJ + S/P2 – Prince Faisal Hospital At RACJ, observed excavation where basalt rock was encountered underground and excavation was stopped. At Prince Faisal Hospital, observed excavation works associated with the extension/helipad works.
Farah’s Monthly Report PG. 41OIP-02-01, Rev.1.0 S S07- 05 Footing reinforcement S/P2 – Prince Faisal Hospital Observed reinforcement preparation and reinforcement bars as part of the structural construction works. S S07- 08 Reinforcement works in columns and walls S/P2 – Prince Faisal Hospital Observed vertical reinforcement and reinforcement assemblies associated with the structural works. S S07- 14 Stone works S/P3 – Jerash Health Center Observed the stone cladding works forming part of the refurbished external envelope. S S07- 23 Wood works S/P3 – Jerash Health Center Observed external architectural works including pergolas as part of the refurbishment scope. S S07- 24 Metal works S/P3 – Jerash Health Center Observed/learned from the metal jacketing added to strengthen the existing structural elements. 5. Any Events / Conferences you participated 6. Your Plan for Next Month. Appendices • Training Plan • Monthly Attendance Sheet • NOS report
Farah’s Monthly Report PG. 42OIP-02-01, Rev.1.0
Month: Six 15/07/2026 Date Day Time In Time Out Total Hours Apprentice Signature 1 7/15/2026 Wednesday 8:15 AM 3:30 PM 7:15 hrs 2 7/16/2026 Thursday 8:00 AM 5:30 PM 9:30 hrs 3 7/17/2026 Friday 4 7/18/2026 Saturday 5 7/19/2026 Sunday 8:00 AM 5:00 PM 9:00 hrs 6 7/20/2026 Monday 9:00 AM 6:45 PM 9:45 hrs 7 7/21/2026 Tuesday 10:00 AM 5:30 PM 7:30 hrs 8 7/22/2026 Wednesday 9:30 AM 6:30 PM 9:00 hrs 9 7/23/2026 Thursday 8:00 AM 5:30 PM 9:30 hrs 10 7/24/2026 Friday 11 7/25/2026 Saturday 12 7/26/2026 Sunday 10:00 AM 6:00 PM 8:00 hrs 13 7/27/2026 Monday 8:30 AM 5:30 PM 9:00 hrs 14 7/28/2026 Tuesday 10:00 AM 6:00 PM 8:00 hrs 15 7/29/2026 Wednesday 10:00 AM 5:00 PM 7:00 hrs 16 7/30/2026 Thursday 10:00 AM 5:30 PM 7:30 hrs 17 7/31/2026 Friday 18 8/1/2026 Saturday 19 8/2/2026 Sunday 10:00 AM 5:00 PM 7:00 hrs 20 8/3/2026 Monday 10:00 AM 5:30 PM 7:30 hrs 21 8/4/2026 Tuesday 10:00 AM 5:00 PM 7:00 hrs 22 8/5/2026 Wednesday 10:00 AM 5:00 PM 7:00 hrs 23 8/6/2026 Thursday 9:00 AM 4:30 PM 7:30 hrs 24 8/7/2026 Friday 25 8/8/2026 Saturday 26 8/9/2026 Sunday 10:00 AM 5:30 PM 7:30 hrs 27 8/10/2026 Monday 10:00 AM 5:00 PM 7:00 hrs 28 8/11/2026 Tuesday 10:00 AM 5:30 PM 7:30 hrs 29 8/12/2026 Wednesday 9:00 AM 4:30 PM 7:30 hrs 30 8/13/2026 Thursday 9:30 AM 4:30 PM 7:00 hrs 31 8/14/2026 Friday 32 8/15/2026 Saturday Attendance Total hrs Workplace Name: Workplace mentor Signature: Daily Apprenticeship Attendance Sheet Workplace mentor: AJi group Eng . Hamza Bustanji Apprentice Name: FARAH ABU ZAID
173:30hrs
OIP-02-02, Rev.1.0 NOS Report Form NOS REPORT MONTH 6 STUDENT NAME: FARAH ABUZAID COMPANY: AJI GROUP Chapter Name of NOS: Number of NOS: 1 Programming & Analysis (Pre Design Phase) 1 2 Project Planning & Conceptual Design 3 3 Design Development, Detailed Design and Construction Informtion 6 4 Project Management 0 5 Supervision 8 6 Construction Management 0 **Performance criteria of the NOS and how you applied it in your company ** Include all the Competencies (Code/The Competency/How you applied it) (Explain and include evidence from your work)
OIP-02-02, Rev.1.0 NOS Report Form Chapter 1 PROGRAMMING & ANALYSIS (PRE DESIGN PHASE) 1.1 RELATED PROJECTS : I will use the Project No. listed in the table below as a reference for each competency. For more details on how each competency was achieved, please refer to the corresponding monthly reports submitted with this NOS report. Project name Project No. Food Festival Project P1 Holiday Inn Renovation Project P2 RACJ Project P3 Prince Faisal Hospital Expansion Project P4 Jerash Health Center – Refurbishment Project P5 1.2 COMPETENCY ACHIEVEMENT Code Competency Name Project No. How the Competency Was Achieved Type PD02- 01 Prepare site analysis diagrams to document existing conditions, features, infrastructure, and regulatory requirements P1 – Food Festival Developed a site zoning plan identifying existing buildings, demolished buildings, and new proposed buildings, as part of documenting and understanding the site. Performance Completed: 1 / 15 Competencies — 6.7%
OIP-02-02, Rev.1.0 NOS Report Form Chapter 2 PROJECT PLANNING & CONCEPTUAL DESIGN 2.1 RELATED PROJECTS : I will use the Project No. listed in the table below as a reference for each competency. For more details on how each competency was achieved, please refer to the corresponding monthly reports submitted with this NOS report. Project name Project No. Food Festival Project P1 Holiday Inn Renovation Project P2 RACJ Project P3 Prince Faisal Hospital Expansion Project P4 Jerash Health Center – Refurbishment Project P5 2.2 COMPETENCY ACHIEVEMENT Level of achievement of the required Programming and Analysis competencies during the internship period. Code Competency Name Project No. How the Competency Was Achieved Type CD03 Select materials, finishes, and systems based on technical properties and aesthetic requirements P1 – Food Festival + P2 – Holiday Inn For Food Festival, developed a material palette for the market models. For Holiday Inn, added material representations and hatches, including insulation, brickwork, and other construction materials. Performance CD13- 03 Communicate design ideas with three- dimensional (3-D) computer aided design software P1 – Food Festival Developed the market/kiosk models in Revit to represent the different design proposals in 3D. Performance CD13- 04 Communicate design ideas with BIM software P1 – Food Festival + P2 – Used Revit/BIM to develop and communicate the market models and to update the Holiday Inn architectural Performance
OIP-02-02, Rev.1.0 NOS Report Form Holiday Inn documentation and material information. Completed: 3 / 17 Competencies — 17.6% Chapter 3 DESIGN DEVELOPMENT, DETAILED DESIGN AND CONSTRUCTION INFORMATION 3.1 RELATED PROJECTS : I will use the Project No. listed in the table below as a reference for each competency. For more details on how each competency was achieved, please refer to the corresponding monthly reports submitted with this NOS report. Project name Project No. Food Festival Project P1 Holiday Inn Renovation Project P2 RACJ Project P3 Prince Faisal Hospital Expansion Project P4 Jerash Health Center – Refurbishment Project P5 3.2 COMPETENCY ACHIEVEMENT Level of achievement of the required Programming and Analysis competencies during the internship period. Code Competency Name Project No. How the Competency Was Achieved Type DD05 Select furniture, fixtures, and equipment that meet client’s design P3 – Jerash Health Center Reviewed project documentation containing equipment information/lists as part of the refurbishment and new medical- service requirements. Performance
OIP-02-02, Rev.1.0 NOS Report Form requirements and needs DD06- 02 Construction materials P1 – Food Festival + P2 – Holiday Inn Applied construction-material knowledge through the Food Festival material palette and by representing insulation, brickwork, and other construction materials in the Holiday Inn drawings. Knowledge DD09 Put together construction information packages P1 – Food Festival + P2 – Holiday Inn + P3 – Jerash Health Center Prepared and organized construction documentation and drawing information for the Food Festival market models, Holiday Inn entrance modification, and Jerash Health Center refurbishment documentation. Performance DD09- 01 Develop construction drawings (plans, sections, elevations, wall sections, details, schedules) P1 – Food Festival + P2 – Holiday Inn + P3 – Jerash Health Center Developed construction/documentation drawings for the Food Festival models; modified the Holiday Inn before/after entrance plan with material information; and worked with architectural plans/elevations for the Jerash Health Center refurbishment. Performance DD11 Contribute to Building Information Modelling (BIM) P1 – Food Festival + P3 – Jerash Health Center Contributed to BIM-based project documentation through the development of Revit models and digital project information. Performance DD11- 01 Build digital models using BIM modelling software P1 – Food Festival Built the market models in Revit, developing the different kiosk proposals into digital BIM models. Performance Completed: 6 / 29 Competencies — 20.7% Chapter 4
OIP-02-02, Rev.1.0 NOS Report Form Chapter 5 SUPERVISION 5.1 RELATED PROJECTS I will use the Project No. listed in the table below as a reference for each competency. For more details on how each competency was achieved, please refer to the corresponding monthly reports submitted with this NOS report. Project name Project No. Al hashemiya vocational school for boys P1 Dubai Bay Island - island B P2 Tuaja Al Madinah P3 VOCO hotel P4 AJWE Building P5 5.2 COMPETENCY ACHIEVEMENT Level of achievement of the required Programming and Analysis competencies during the internship period. Code Competency Name Project No. How the Competency Was Achieved Type S07 Inspection and Approval of Construction Works P1 – RACJ + P2 – Prince Faisal Hospital + P3 – Jerash Health Center Participated in site supervision and observed/inspected construction and refurbishment activities across the three sites. Performance S07- 01 Surveying works: site boundaries and street alignment P1 – RACJ + P2 – Prince Faisal Hospital At RACJ, observed benchmarks and site levels and identified discrepancies between project level information. At Prince Faisal Hospital, observed site setting-out/surveying activities. Performance S07- 02 Excavation works P1 – RACJ + P2 – Prince Faisal Hospital At RACJ, observed excavation where basalt rock was encountered underground and excavation was stopped. At Prince Faisal Hospital, observed excavation works associated with the extension/helipad works. Performance
OIP-02-02, Rev.1.0 NOS Report Form S07- 05 Footing reinforcement P2 – Prince Faisal Hospital Observed reinforcement preparation and reinforcement bars as part of the structural construction works. Performance S07- 08 Reinforcement works in columns and walls P2 – Prince Faisal Hospital Observed vertical reinforcement and reinforcement assemblies associated with the structural works. Performance S07- 14 Stone works P3 – Jerash Health Center Observed the stone cladding works forming part of the refurbished external envelope. Performance S07- 23 Wood works P3 – Jerash Health Center Observed external architectural works including pergolas as part of the refurbishment scope. Performance S07- 24 Metal works P3 – Jerash Health Center Observed/learned from the metal jacketing added to strengthen the existing structural elements. Performance Completed: 8 / 30 Competencies — 26.7% Chapter 6
OIP-02-03, Rev.1.0 Final Report 7TH MONTH REPORT 15/8/2026-15/9/2026
Email 22110059@htu.edu.jo Phone 0799864046 Address Amman Apprenticeship ReportSchool of Built Environment Engineering Apprenticeship Monthly Report Student Name: Farah Abuzaid Student ID: 22110059 Major: Architectural Engineering Apprenticeship Mentor:Arch. Jomana Alawi Company Name: AJi group Industry Mentor: Eng . Hamza Bustanji Date of Report:8/15/2026 Report Type: Seventh Monthly Report Dates: 8/15/2025 – 9/15/2025
Table of Contents I. Apprenticeship Monthly Report ........................................................................1 II. General Introduction ..........................................................................................1 III. Section 1: Office Work (Design Phases) ............................................................1 Project 1 ......................................................................................... Error! Bookmark not defined. Task 1 : change links in rivet for the hotel rooms ...................... Error! Bookmark not defined. Task 2 :change the rooms name according to the new room matrix excel file .............. Error! Bookmark not defined. Task 3 :sheets new room legend ................................................. Error! Bookmark not defined. Task 4 :the output in pdf format .................................................. Error! Bookmark not defined. List of Achieved Competencies: ................................................... Error! Bookmark not defined. Project 2 ......................................................................................... Error! Bookmark not defined. Task 1 : Imported and developed the office plans from PDF drawings into a Revit model, including the surrounding streets, site levels, and road slopes. ............. Error! Bookmark not defined. Task 2 : façade design studies and elevation ............................. Error! Bookmark not defined. List of Achieved Competencies: ................................................... Error! Bookmark not defined. IV. Section 2 : Site Supervision ...............................................................................3 V. Section 3 : Project Management...................................................................... 20 VI. Section 4: Executive Summary ........................................................................ 42 VII. Appendices........................................................................................................ 43 Training Plan .................................................................................. Error! Bookmark not defined. Monthly Attendance Sheet ........................................................... Error! Bookmark not defined. NOS report ..................................................................................... Error! Bookmark not defined.
Farah’s Monthly Report PG. 1OIP-02-01, Rev.1.0 General Introduction Section 1: Office Work (Design Phases) Meeting with Eng. Doaa – BOQsSpecifications • Attended a meeting with Eng. Doaa to learn about the preparation of Bills of Quantities (BOQs) and Project Specifications. • Discussed how quantities are identified from drawings and organized into BOQ items according to the project scope. • Learned about the role of specifications in defining materials, workmanship, technical requirements, and quality standards. • Understood how BOQs and specifications work together with the project drawings as part of the tender and construction documentation. Detailed Program
Farah’s Monthly Report PG. 2OIP-02-01, Rev.1.0 Presentation by Eng. Abu Rummaneh – Regulatory Approvals • Attended a presentation by Eng. Abu Rummaneh about the process of preparing and submitting project documents for regulatory approvals. • Learned about the required documentation and submission procedures for authorities such as the Jordan Engineers Association and Civil Defense. • Discussed the importance of coordinating and completing the required drawings and documents before submitting them for approval. • Gained an understanding of the architect’s role in supporting the project approval process. Construction Technology – Food Festival Project • Reviewed the Food Festival project as a practical example to understand construction technology. • Discussed the construction systems, materials, façade elements, and construction processes used in translating the design into the built work. • Learned how architectural details and material selections relate to the construction method and sequence. ___________________________________________________________________________________ List of Achieved Competencies: Code Competency Achievement Level How It Was Achieved DD09- 02 Survey quantities to prepare BOQs Knowledge Learned through a meeting with Eng. Doaa about BOQ preparation. The session explained how quantities are taken from drawings, organized into BOQ items, and related to the project scope and tender documentation. DD09- 03 Develop project specifications Knowledge Learned through the same session with Eng. Doaa, where the role of project specifications was explained, including defining materials, workmanship, technical requirements, and quality standards alongside the drawings and BOQ. DD06 Apply knowledge in Construction Technology Knowledge Developed through reviewing actual project examples, particularly the Food Festival project, and discussing how architectural designs are translated into construction
Farah’s Monthly Report PG. 3OIP-02-01, Rev.1.0 systems, materials, details, and construction methods. DD06- 01 Construction Systems Knowledge Through the Food Festival project, I learned how the building's construction systems and architectural elements are assembled and coordinated, including understanding the relationship between the structural and architectural components. DD06- 02 Construction Materials Knowledge Through the Food Festival project, I reviewed the materials used for architectural and façade elements and learned how material selection relates to the design, application, and construction requirements. DD06- 03 Construction Processes Knowledge Through project examples and construction discussions, I learned how construction progresses from the drawings and selected systems to the actual execution of architectural elements, including understanding the sequence and coordination required during construction. DD03 Prepare submittals for regulatory approval Knowledge Learned through a presentation by Eng. Abu Rummaneh explaining the process of preparing and submitting project documents for regulatory approval, including submissions to the Jordan Engineers Association and Civil Defense, and the required documentation and coordination before submission. Section 2 : Site Supervision During July, I focused on developing my knowledge in Construction Management through a combination of site visits and internal learning sessions. This month, I visited the Royal Automobile Club site, where I was introduced to construction-related processes
Farah’s Monthly Report PG. 4OIP-02-01, Rev.1.0 and reviewed actual project documentation, including shop drawings and As-Built drawings. In addition, I attended several Construction Management lectures and discussions with the Supervision Team at the office, including sessions with Eng. Arwa and Eng. Marah. These sessions covered different aspects of construction management, project scheduling, shop drawings, construction monitoring, inspections, approvals, and the coordination and resolution of construction-related issues. Most of the competencies developed during this month were achieved at the Knowledge level, as I was mainly learning through explanations, discussions, reviewing actual project documents, and observing construction practices during the site visit. My Notes :